25 August 2014
VERY busy day… and
absolutely PERFECT weather. Perry arrived shortly after 7, having been to
Goodro’s to hand-select the 2x6’s that will become the hip rafters in the sauna
building (they have to be dead straight) and to Green Mountain Power, who did
not have the ¾″ 22° bend (I thought) I needed to finish the electrical conduit
run into the sauna building. So we faked
that bend by bowing the conduit, then quickly buried the results so
nobody-will-ever-know! Kevin got here
while all this was going on to continue adding brick to the chimney top.
Goodro’s delivery truck also interrupted the proceedings, bringing the sauna
building exterior and pocket doors plus all the rest of the roof framing 2x6’s.
Meanwhile, back in the trenches, I sucked a string though the electrical
conduit, used that string to pull a ¼″ nylon line through, and used that line
to pull the power wires through. A LOT
of pulling, by the end of which I had a severe case of left tennis elbow. But by 9:30 we had power to the people
sauna building! Perry and I built and
installed the wood beams that will support the southwest corner of the
building, then put on the top plates for all the walls, nailing them firmly to
the wall bottom plates (that are actually at the top of the wall, ‘cause the
plates at the bottom of the wall are called sole plates). Confused yet? We realized (at the end of the day as we were
putting tools away) that we had forgotten one important step at this
point. Okay, students, what did we
forget to do? After lunch, while Perry
ran string around the building perimeter and used those reference lines to
straighten the walls (which were already pretty straight), I laid the bottom 30
feet of the 1½″ conduit that will house a water line from the house to a spigot
by the sauna building, said water to be used to create steam to obfuscate the
viewing of old fat naked guys taking the cure.
We then started putting ½″ pressure treated plywood sheathing on the
walls. Meanwhile, atop the house, Kevin finished laying brick (using 356 of the
525 that came in the cube), then built a form and poured a 3″ thick concrete
chimney cap. For future reference: the
flue length from the basement cleanout to the top of the chimney is 28
feet. Perry and I finished the workday
strategizing options for correcting the oversight of not shimming the top
plates so that they formed a perfectly level surface onto which we could build
the roof. By this time it was 6 o’clock,
much too late to start a fire to grill the steak I was planning for dinner, so
instead did my annual swim across the lake and back. That accomplished, I nuked a dinner that said
it would feed three people. For some
reason I’m still hungry after finishing the entire thing, a 12 oz. adult
beverage, plus a huge dessert…