The brothers LaFlam
(Sean & Ben) spent the day putting sheathing on the east and south sides of
the roof. I thought I had been paying my
Goose Creek bills on time, but maybe not, ‘cause late morning Ben “accidently” lost
control of a large piece of sheathing, which came sliding off the roof, but did
not slice my head off. Instead, it hit
me in the left side ribs, where I do have lots of padding. Fred spent several hours putting up even more
joist hangers, then worked with Perry for the rest of the day installing the
rafter tails and outlooks on the north side of the house. Kevin Haight arrived at 8 to get set up for
building the chimney. Goodro’s boom
truck got here at 8:30 with a good-sized load of concrete block, flue pipe,
cement, and concrete mix. I spent the
day in the cellar with Kevin helping (and learning) while he laid the first six
courses of block.