You know Delores has a
mouse problem when you capture two in the same trap. Yes, that’s right, meece numbers 13 and 14
were snuggled up together when I arose this morning. How cute!
After releasing them back into the wild, I did the 150 hour servicing on
the Kubota while waiting for Kevin The Mason (as opposed to Kevin The Roofer) to
arrive. When he did, at 9, he was
somewhat disgruntled that Goose Creek had hauled away all their staging last
week. So Kevin immediately returned to
his abode to get his own staging, arriving back at Fern Lake at 11:30. I spent the morning cleaning / picking up the
construction site, then staging concrete block and bags of cement mix where
Kevin wanted them (on the future patio).
Staging erected, Kevin got to work raising the house chimney up through
the roof with a couple more courses of 8″ concrete block, attaching the second
roof hip support bracket as he went. Then he transitioned to 4″ block, using
that to build the chimney core up to the required height (3 feet above the roof
peak). I helped as needed, hoisting
block and bucket-loads of concrete and cement mix up onto the staging. Discovered, early on and most disconcertedly,
that my New Balance working shoes are woefully inadequate to walking on the
roof. Life was just a little too
exciting for a few seconds there! In
between playing mason tender, ran ¾″ PVC conduit in the trench from the top of
the wood walkway down to very close to the sauna building… need a few more
fittings to finish that job tomorrow.
For future reference, the electrical conduit is parallel to and 6 feet
north of walkway section 3, and will be buried about 2 feet below grade level
along that stretch.