31 May 2014

Off to Goodro’s early morn to put the first color coat on the two steel beams.  Met Alverta at a rendezvous along US 7 and guided her back to Fern Lake, arriving a few minutes before Alex, Katy, & Devin, up for the weekend from the Boston environs.  After a tour of the premises, Alex and I installed the radon abatement piping by cutting out a section of Blueboard, digging out the sand and stone underneath to make a shallow trench, putting in the holey pipe I had fabricated, and, finally, reinstalling the foam over top.  Marty came up early afternoon to kindly offer use of Chez Lapidus for the cookout planned for later.  As it was a cold, windy, cloudy day, we gratefully accepted.  Sitting around an hour later enjoying a pre-prandial beverage (or two) while staying warm by the campfire, the sun came out and the wind abated.  So canceled our off-site dining reservation and started grilling burgers.  Lynne brought a large garden salad and desert, Merry came with her famous orzo salad, Alverta provided potato salad, beanies and weenies appeared by magic, and Dolores contributed many fluid ounces of imminently potable libations.  After the dishes were done, Alex, Katy, & Devin took possession of the RV and I went down to bed at Marty & Merry’s.


 


30 May 2014

Only made three trips to Goodro Lumber today… Could have been worse.  First trip was crack of dawn early to prep and apply primer to the two additional steel beams we’ve decided to use to support the house Main Level.  Using steel instead of LGL (lumber glue laminate) beams is not only safer in case of a fire, but less expensive to boot.  Got back to Fern Lake at 11 to find Jimmy hard at work back filling the foundation and Sean, Ben, and Ty Zimmerman nearly done with installing the under-slab foam insulation in the cellar.  Just before Sean and his crew departed, he gave me a list of tasks to accomplish this weekend: making and installing the radon gas abatement piping, spray foam sealing the under-slab foam insulation, and putting onto a drawing all the measurements needed to install the under-slab radiant heating piping.  Right after lunch Jimmy asked me to go to Goodro’s to pick up some more fittings needed for the perimeter drain installation.  Brought back Schedule 40 PVC fittings (‘cause that was what Chuck used for all the under-slab drains) only to learn that there is specific sewer and drain pipe (which is what Jimmy was using for the perimeter drains) and, no 4″ PVC does not fit 4″ SDR.  So back to Goodro’s I went.  The difference in price between the two types of fittings almost paid for the gas I burned making the exchange.  Jimmy and I installed a vertical branch off the perimeter drain to which a grate will be fitted to catch water coming off the roof valley onto the Patio.  Had him put a ton of stone (literally) all around that vertical pipe so water will have no excuse to stay on the Patio surface.  Jimmy then commenced digging the trenches for the Garage frost walls.  Right in the southeast corner he uncovered a 2-ton rock, which made that corner of the trench extra big... severing the footpath over to the wood walkway.  James came for his after work job and used the skid-steer to move to the north side of the house the smaller rocks and dirt Jimmy was digging out.  That done, James and I lugged the detachable section of the wood walkway up the hill and made a temporary bridge across the Garage frost wall trench, suitable for 90 year old ladies to cross.


 

 

29 May 2014

Wink pulled up just after 7 to trade Jimmy’s “small” grade-all excavator (John Deere 120C) for the JD160C, needed on another job. Spent another hour moving stone around in the cellar hole until Jimmy got here with his skid-steer and compactors. The two of us then spent two more hours rearranging and compacting stone so that, by 10 o’clock, the cellar floor was back to the same condition it was in last Thursday, albeit now with a bunch of PVC pipes sticking up through the surface.  Wink brought us a load of sand that Jimmy and I spread over top the stone… Jimmy spreading (with his excavator and skid-steer) and raking (‘cause Jimmy is just as good at raking a smooth, level surface as he is at everything else, i.e., fabulous), me shoveling, checking grade with his laser leveler, and compacting.  By lunchtime the cellar was ready for polyethylene sheeting and seven Kubota payments worth of polystyrene foam.  In the 23 days since Jimmy dug the cellar hole, many rocks have fallen off the banks and fetched up against the foundation footers. After lunch Jimmy and I moved all those rocks out of the way, by hand.  Then we hand shoveled a trench next to the footers.  Into that trench Jimmy placed a layer of stone using his JD120C.  Because the bucket can be tilted in any direction (which is why they call it a grade-all), Jimmy could literally pour stone wherever he wanted it.  Beyond tricky!!!!  Jimmy then put 4″ perimeter drain pipes (aka weeping tiles) in the footer trenches, bedded them so that water would flow from a high point in the middle of the house east side towards two termination points at either end of the west side.  He then poured another foot of stone over the pipes.  I got plenty of exercise wielding an idiot stick to keep the stone level.  Over top of all that stone we spread filter fabric, which will keep dirt from leaching into and clogging the stone and perimeter drains.  I took Jimmy over to his shop on Upper Plains Road so that he could bring a dump truck (loaded with more sand) over here, ready to move the stockpile of backfill dirt from next to the driveway down to the house foundation.  But that’s tomorrow’s story…  After a heavy day of hot and dirty work, the lake was as refreshing as always.  So was the Sam Adams Boston Lager!

 

28 May 2014

Jimmy Ploof came bearing gifts (a truckload of stone for bedding the perimeter drains) just on 7:30.  Chuck pulled in at 8 and continued putting in the under-slab plumbing conduit.  I built a 14″ square by 5½″ deep box that will be used to keep part of the floor under the Guest Bath shower concrete-less, ‘cause we won’t know exactly where the drain will be located until we buy that shower, many moons after the cellar floor concrete is poured.  I also dug more trenches and helped Chuck whenever he needed an extra hand or two.  Used a hand sledge and cold chisel to notch the footers in two places so that plumbing stacks for the Main Level could be run from under the slab into the wall without being seen.  Early afternoon Jason and Nate came back and, in short order, sprayed a tar and rubber compound over all the below-grade portions of the exterior walls.  While that was ongoing, the Goodro Lumber delivery truck arrived with the closed-cell polystyrene foam (aka Blueboard) that will be used to insulate under the cellar floor. Boy is that stuff E∙X∙P∙E∙N∙S∙I∙V∙E!!!! Somebody (Dow Chemical?) is raking in the big bucks with that product. The driver was pleased to see that the Kubota has forks… which made unloading the truck a lot easier than moving 120 4x8 sheets by hand. Chuck finished his work and left at 3. I then spent another 3 hours moving stone around, trying to at least approximate the conditions that obtained before Chuck started the plumbing rough-in.






27 May 2014

While waiting for all and sundry to arrive this morning, drilled the hole for the sauna French drain and lined the bottom of the barrel with previously washed stones.  Sean showed up shortly after 8, just as I was finishing that job.  Chuck Ringer from Ryan’s Plumbing got here around 9 and we began laying out the under-slab waste drains that will convey liquids to the septic tank.  Dennis Senesac made his appearance mid-morning to consult on the piping layout.  On a very positive note, Dennis had been in touch with his geothermal guru and preliminary indications are that a ground-loop energy recovery system is possible, the trenches may be shorter and the depth shallower than I had expected, but there is concern about putting the coils under the driveway.  More to follow…  After Dennis left, I used the backhoe to dig the first trench for Chuck, for which he was duly appreciative, since normally all under-slab trenches have to be dug by hand… his hand.  Sean and I set chalk lines around the exterior foundation walls to show the limits of where we want the waterproofing sealer to be applied.  Steve Poplawski from Ryans pulled in early afternoon to help Chuck.  I continued digging trenches with the backhoe, seriously disrupting the compacted stone that Jimmy Ploof and I had put in on Thursday last.  Jason Day and Nate Pettys from Northern Vermont Pressure Seal arrived at 3.  They quickly prepped the exterior walls for waterproofing.  Just as they were about to start spraying sealer, a thunderstorm came rolling though… ending all work for the day.  Everyone left.  Wisely, I had put my computer and camera in the back of Chuck’s truck in case it started to rain.  Not so wisely, he drove off before I remembered that minor critical detail.  I chased him all the way up the driveway and (seemingly) halfway to Fernville Road before he spotted that he was being pursued by an arm-waving drowned rat carrying a broom (don’t ask) in a completely ineffective yellow raincoat.  Crises averted, took shelter in the RV, replacing my outer clothing with drier versions.  At 5 the sun came out, so went back to work.  Installed the sauna drain.  Then spent some fun time removing from the house cellar all the large rocks I had dredged up from today’s excavations and rough backfilling the first couple of trenches.  Quit when it started raining again at 7.




26 May 2014

The long-range forecast said today was supposed to be like yesterday.  That forecast was not accurate.  Unfortunate, ‘cause I had invited the Lapidii up for steaks-on-the-cook fire based on the forecast.  Did manage to sear some cow between rain showers, so that turned out well.   Also washed both trucks between rain showers, so the day wasn’t spent in total idolatry. In spite of not getting sprayed last night, there were very few mosquitoes out, the few times I was.

25 May 2014

An absolutely gorgeous day… mostly spent shoveling dirt down in Mosquito Central (aka: the Sauna Building hole).  Good thing I’m a major investor in the S.C. Johnson Company (maker of Deep Woods Off).  Got the area around the footers leveled out and the area in what will be the actual sauna graded and ready for the final batch of concrete.  Did take an hour mid-afternoon for some sunbathing and swimming.  Sure that time will be docked from my pay, the boss being a no-fun kind of guy.  The mosquito control spray truck was in the neighborhood just before bedtime… but did not deign to come down the ΔO driveway!

24 May 2014

Another rainy morning, great for doing more construction drawings.  Weather broke early afternoon so used the Kubota to fill in a couple of mud holes at the RV campsite, using rock and sand scavenged from Friday’s deliveries.  Then I spent an hour sharpening Mr. Jonsered, who was looking somewhat the worse for wear after hitting a small rock during his last outing.  To finish out the day, spent some more time organizing the Shed upper level… which is finally in good enough order to be going forward with.

23 May 2014

Woke up to the sound of rain and the nightmare realization that I’d put two of the west frost wall penetration sleeves in the wrong place.  Did some drawings needed for next week’s planned construction, talked to Sean, and eventually figured out how to correct the wall penetration problems with minimal fuss and bother.  Jimmy stopped by mid-afternoon to retrieve his skid-steer.  On the few occasions when I ventured outside between rain showers the mosquitoes were REALLY BAD!  Called the BLSC (Brandon, Leicester, Salisbury Commission) and requested a spraying, as the cries of the children being carried away by the swarm were most pitiful.

22 May 2014

5 o’clock Thursday and the start of a four-day weekend, so kickin’ back, writin’ me blog, and havin’ a Bud.  Yep, since Sean has been spot on with all his recommendations so far, figured I’d try the beer that he prefers and, you know, that brew ain’t half bad.  Sean arrived at 7:30 and, not having a long list of house building issues to discuss, regaled me with stories about the adventures of owning a boat. Jimmy Ploof got here about 9 to start backfilling the west frost wall and putting down the compacted crushed stone that will be the next to bottom layer in the cellar floor matrix, consisting of: 7,926 miles of earth (some of it molten), 4″ – 48″ of 1¾″ crushed stone, 6 millimeters of polyethylene sheeting (vapor barrier), 3″ of closed-cell polystyrene (insulation), 4″ of 2,500 psi concrete, and the finished floor (tile, carpet, whatever).  Over the course of the day Wink Rhodes brought in 6 truckloads (about 84 cubic yards) of stone for the cellar and 3 truckloads of sandy gravel backfill for the exterior side of the frost wall (cheaper than having Jimmy find suitable material by pawing through the “stuff” that came out of the cellar hole).  James Ploof came at 3:30 for his after-school job, using the skid-steer to spread stone around, something he learned to do when he was 10…  My job throughout the day was to help shovel stone, when shoveling stone was needed, plus Jimmy had me operate the compactor for much of the afternoon.  During breaks I moved all of the leftover wood walkway construction lumber out of the car-turnaround area and then took a stab at organizing the mess in the shed upper level.  After every rain shower kept finding more nails in areas that I would have sworn were “clean”.  It’s like they were sprouting!  Also sprouting are the mosquitoes!

 

 

21 May 2014

Mosquitoes were out in force this morning and evening.  Kevin, Victor, and Ben came at 8 and continued loading the Long Ridge trucks with all their concrete forms and associated gear. By 9 that job was done and the crew joined me in breaking form ties, finishing that not-so-pleasant task by 10.  Once the Long Ridge folks had headed for greener pastures, I used Perry’s big magnet to collect nails, rebar ties, form tie ends, and other scrap metal that were thick on the ground in the cellar hole.  Got 22 pounds, destined for recycling.  Just as I was wrapping up that activity, heard the beep, beep, beep of a piece of heavy machinery up on the driveway.  It was Jimmy Ploof, dropping off his John Deere skid-steer, which he will be using tomorrow.  I then spent a couple of hours getting all the big rocks out of the cellar hole (actually, dumped them in the frost wall trench).  VERY hot, sweaty, and dirty at that point, discovered that the lake temperature was up to 68°, so took the plunge for the first time this year.  Brisk, but refreshing! Lynne came by to check on progress as I was enjoying a late dinner.

20 May 2014

Woke up at 5 am with an epiphany.  Why don’t we run a ground-loop geothermal system under the driveway, since we’re already going to dig up ⅔ of its length in order to run the water line from the well to the house?  Sent those thoughts off to Dennis and Sean in an email.  Sean arrived at Fern Lake just as he got that missive.  Perfect timing!  Larry, Rick, Kevin, Victor, Scott, and Ben also got here about the same time and began prepping for three concrete pours planned for this morning.  Sean left after he and I had caught up on current and near-term planned events… and all the changes to the house specifications document.  Soon thereafter a Carrara mixer lumbered down the driveway yet again, this time with only half a load.  By 10 we had poured a nice floor for the Shed lower level, put concrete in the footer for the house chimney, and dumped 4 wheelbarrow loads into the form for the sauna stove pad. The Longrridge crew then began the laborious process of stripping forms off the cellar walls and lugging those beasts out of the hole.  Talked to Dennis and got the cost (from Spaffords) to drill three 200 foot wells for a vertical closed-loop geothermal system.  Expensive, but just barely within budget.  Certain that a ground-loop system would be far more pocketbook-friendly, Dennis is going to consult with his geothermal engineers to see if a system such as I proposed could work. I then spent the rest of the morning pulling and de-nailing cleats used to hold the concrete forms in place.  Sometime around midday Jimmy LaFlam (Sean’s & Ben’s father) visited.  We had a nice chat, after which Sean’s ears were probably burning.  (Ben got off easy… this time.)   After lunch Larry taught me how to break off form ties, which you do by swatting them back and forth with a hammer.  He made it look very easy.  It’s not.  By the end of the afternoon my right forearm was pretty much dead.  Also by the end of the afternoon the shed garage floor still had not taken an initial set (most likely due to the low temperature and high humidity in those nether regions), which meant that it couldn’t be floated, which meant that Rick’s wife was not at all pleased that he couldn’t come home on time for dinner.  Once Larry and the rest of his gang were gone, made a quick trip into Brandon for the usual (the flavor this time is Sugarloaf Mint Chip).  Rick had FINALLY been able to float the floor while I was gone.  A quick Bud consumed, so was he, and I settled down for some burgers and dogs hot off the campfire… and my own Allagash Triple Ale.  Oh, yeah, remembered to call Chree to wish her a happy anniversary.  She seemed to recognize the name of the guy she’s been married to for the last 42 years…

 

19 May 2014

Was just getting out of bed when Rick arrived to start work.  Guess doing laundry yesterday took more out of me than I realized. Larry, Kevin, Victor, and Scott got here at 8, by which time I, too, was ready for work.  While the Long Ridge gang put the final bits and pieces of the cellar wall forms together, I continued working on and printing out the latest round of changes to the house specifications documents.  At 1 Carrara’s pump truck arrived.  With a reach of 95 feet, seemed adequate for the job.  The first (of four) fully loaded concrete mixer pulled in at 1:30.  By 3 all 41 cubic yards of 3,000 psi concrete had been transferred from the mixers to the cellar wall forms.  The Long Ridge crew left at 4:30 with all the walls floated, J-bolts inserted, and the ΔO logo and MAY 2014 scratched into the Porch threshold.  Dennis called to say he had finally traded voicemails with Spafford's.  That was the good news.  The bad news is that, according to Spafford's, an open-loop geothermal system is completely out of the question in this neck of the woods.  More news at 11.  A monster chef’s salad for dinner, starring a bunch of blanched asparagus fresh from Lynne & Perry’s garden.


 


18 May 2014

Spent the day at Lynne & Perry’s doing four loads of very dirty laundry and, in spite of it not being the hottest day of the year, helping move seven pickup truck loads from the mounds of split firewood to the stacked-and-ready-for-next-winter racks near the house.  Don’t tell Perry, but by the end of the day I was pretty worn out!

17 May 2014

Back to Goodro’s once again to put the final coat of paint on the steel beam.  Then, even though the overnight rain had abated, spent the day ensconced in Dolores catching up on cost accounting and making all the changes to our house specifications document engendered by the HVAC and other recent decisions. Those of you who know me well will think a major malady has befallen, as I took a two hour nap this afternoon.  Must have been considerably sleep depraved from having awoken most of this week around 4 am, with my brain all a tizzy thinking about the upcoming day’s agenda.

16 May 2014

Off to Goodro’s again first thing this morning to put the first color coat of paint on the steel beam and pick up some fittings for the cellar wall penetrations.  Back to Fern Lake shortly after 9 to find Larry and The Gang (Rick, Kevin, Victor, and Scott) busy tying rebar.  Given the soil type found here in Leicester (sandy rocky gravel) and the wall height we’re putting in (8′ 8½″), the 2012 International Residential Building Code calls for vertical rebar 41″ on center with two courses of horizontal rebar, the first 12″ below the top and the second in the middle of the wall.  Larry put in vertical rebar 18″ on center and 6 courses of rebar horizontally.  That wall ain’t never breaking!  Larry and I spent some quality time putting sleeves in the forms for the many thru-wall penetrations needed for utilities running into and out of the house.  Awaited a call / email from Dennis Senesac all morning to confirm the size wall penetrations needed for the potential geothermal system.  Hearing nothing, had to fake three sleeves and have fingers crossed they are the right size and in the right location.  At noon had to run back to Goodro’s to exchange the conduit couplings I bought this morning for a larger size.  Returned to Fern Lake just as the crew was finishing lunch, so joined them for an entertaining (and very dirty) afternoon of putting up forms for the inside of the walls.  That is a tricky operation, as all the form ties (20 per 4x8 sheet of plywood) have to be threaded through holes in the form from the inside out.  Needless to say, the pros from Long Ridge (near Dover) knew all the little tricks to make that job, if not easy, at least not excruciatingly frustrating.  My job was to slide ½″ smooth steel rods through the loops in each row of ties, thereby locking the forms together and reinforcing them.  By beer time the wall forms were complete except for the boards that will form the top 8½″ of the walls… a job for Monday morning.  As I was inhaling some pizza as a late lunch / early dinner, Dennis called to say he STILL has not heard from Spafford's… and that the 2″ sleeves I put in the walls for the (hoped for) open-loop geothermal system… really should have been 3″.  Oh, fudge!


 


15 May 2014

Drove into Goodro’s to prep and prime the 43′ 9″ W10x15 steel beam that will hold up the middle of the house Main Level.  (TMI: the W means it is a “web” beam, commonly known as an I-beam; 10 means the beam is 10 inches high; 15 means it weighs 15 pounds per lineal foot; and the beam top and bottom flanges are 4″ wide.)  So, doing the math, the beam weighs in at a svelte 671 pounds. That is an important number, as you’ll see. Four of the more stoutly built Goodro’s folks most kindly moved the beam into their (rather large) maintenance shop and set it on a couple of sturdy sawhorses for me to work on.  The beam was raw steel and slightly rusty, so sanded it down before applying a premium-quality rust-inhibiting primer paint.  In order to work on all sides of the beam, obviously I had to turn it over, which was within my abilities going from the skinny (4″) to the fat (10″) side, but was just a bit beyond my strength going the other way.  No problem!  Whenever I needed to turn the beam back upright, one of the Goodro’s folks came right over and the two of us did the he-man thing.  Got back to Fern Lake, with all vertebral disks intact, at 11:30 to find Larry, Kevin, Rick, Victor, and Scott busily erecting concrete wall forms. Early afternoon Sean stopped by to see how things were going and discuss / resolve the current crop of issues / questions.  I swear the house is on springs: yesterday Larry told me he had to raise it up an inch (due to a high spot on the footers) and today he told me he had to lower it back down an inch and a half (due to a low spot, he said, in his brain when he calculated the intersection height of the frost wall and the cellar floor).  By the end of the day the exterior side of all the wall forms were set up with their form ties inserted.  [Further TMI: form ties are a twisted metal device with a loop at each end that are used to keep the concrete forms from spreading apart as the concrete is put in.  At the bottom of an 8 foot wall, concrete exerts a force of 1,200 psi on the forms until it sets.]  I helped with the latter activity, as there is a form tie every 12″ horizontally and 20″ vertically, i.e., about 910 of those critters in them thar walls. Had a long HVAC conversation with Matt Sergeant at the close of business.  Then an even longer conversation with Chree about all the decisions recently made and forthcoming with respect to how we want the house built.  The lake temperature is up to 62°; a few more degrees and another really hot day…

 

14 May 2014

Pulled the forms off the sauna building footers while Larry, Kevin, Victor, Scott, and Rick Martell did the same to the house footers.  Somehow they won that race. Sean stopped by to check on progress and take away some of the materials needed so he can make the many penetrations that have to be put in the cellar walls for incoming power, telephone, water, etc. and outgoing power, water, and septic waste.  Made the form for the concrete pad the sauna stove will sit on and discovered that the sauna French drain would be right underneath that pad.  That wouldna work so good!  Tammy, of course, had use of the backhoe when she installed the 55 gallon drain barrel in the (wrong) spot I specified.  So had to hand dig that barrel back out of the ground.  Had accomplished that task, with much sweat expended, by late morning.  As I was about to put the barrel back into its final resting space two of the banks collapsed.  Lunch time!!!!  Finished reburying the barrel and placing the sauna stove concrete pad form just before time to leave for an eagerly anticipated meeting the Sean and Dennis (at Dennis’ office in Vergennes) to make final decisions about the HVAC system for the house. A very productive meeting… and the price plummeted drastically based on the system design Chree and I had agreed on coupled with the energy use modeling done by Matt Sergeant (Efficiency Vermont).  Still no word from Spaffords (well drillers) on whether the water quality in this area is suitable for use in a geothermal energy system.  After our meeting with Dennis, Sean took me just around the corner to the house he just bought… and will move into just as soon as he finds some free time.  With triple pane windows and doors, 18 inch thick walls with R60 insulation (R30 is what our Fern Lake house will have), R80 ceiling insulation (we’ll have R50), the ANNUAL heating and cooling cost last year was $261. The builder (not Sean) won all sorts of energy efficiency innovation awards for that house… and many commissions to build more.  While admiring the house features, met Ashley, Abigail, and Tucker, Sean’s wife and kids.




13 May 2014

Spent the morning putting rebar in the sauna building footer trenches then moving more dirt and rocks around down at that site.  Larry, Kevin, Victor, Ben Cook, and Scott Messer all arrived about 11:30, ready for some football to pour concrete.  The Carrara truck, fully loaded with 11 cubic yards of 3,000 psi concrete, arrived at 12:45 and then the hard work began, wheelbarrowing and shoveling the mix into the house footer forms.  I helped with the shoveling for awhile, then was giving the task of inserting the vertical rebar into the forms that will tie the footers to the cellar walls.  The house footers filled and floated (i.e., smoothed off with a trowel), the driver estimated he had a ½ yard left… and I had calculated that we would need about a yard and a quarter to do the sauna building pour.  So Larry ordered another yard to be delivered while his crew began the arduous task of taking wheelbarrow load after wheelbarrow load of very heavy concrete down the wood walkway to the sauna site.  Kevin and I spread the mix around and then floated the top surface smooth.  I put the J-bolts in very carefully (they hold the building to the foundation) and then discovered, much too late to move them, that I had put them all 5¼ inches from the outside edges of the footers instead of the 6¼ inches that they were supposed to be.  Marty & Merry came up to review progress, then, having heard my tale of woe vis á vis the sauna building bolts, invited me down to their place for some scotch and steak… in that order.  The12 year old helped considerably to ease the pain. The steaks and potato salad came from Dave’s Ferndale Store (very local) and were exceptionally good… as was the 2012 Blackstone Pinot Noir that we washed them down with.  

 

 

12 May 2014

0800 and everybody arrived at once: Perry to help me with putting in the forms for the sauna building footers, Larry, Kevin, and Victor to put in the forms for the house footers, and Sean to talk about the usual host of details needing to be resolved as he plans the next phase of the house construction.  After thrashing out the issues with Chree over the weekend (and thrashing is the correct term!), told Sean what we I want to do for the HVAC system, subject to a “final” meeting with Dennis Senesac, now scheduled for Wednesday afternoon.  Sean and I agreed that the steel beam that will support the middle of the house should extend wall to wall across the whole house vice the shorter version that I had designed.  Mid-morning Tammy stopped by to borrow my Kubota to do some firewood gathering over at Marty & Merry’s place.  By the end of the day Perry and I had the sauna building footer forms in place, square and as level as we could get them using my leveling sight and Perry’s 6-foot level.  We had to remove countless large boulders from the footer trenches in spite of all the digging (and rock removal) I had done yesterday.  Think we’ll both sleep well tonight!  Larry and company had likewise finished the forms for the house footers and put in the rebar reinforcing steel… so those forms are ready for concrete.


11 May 2014

An absolutely perfect day weather-wise… and NO bugs!  After yesterday’s work with the rebar cutter / bender, weren’t movin’ nearly so fast as usual come daybreak.  Much worse after spending the morning hand digging the sauna building footer trenches to their proper depth.  Only hit, and had to dig out, seven, yes seven, 100 pound plus boulders.  After lunch, cut a bunch of 2x6’s salvaged from the old stairway (that ran from the Glassner’s place down to the waterfront) to the lengths needed for the sauna building footer forms.  Stopped work early in order to prepare Dolores, food, and me for having the Lapidii come for the first barbeque of the season.  Another delightful repast with our good neighbors to the north.  Enough liquid painkillers were ingested to at least dull most of the aches and pains resulting from this “relaxing” weekend.

10 May 2014

Lots of rain this morning so spent that time doing more detailed drawings needed for the next phase of the house construction.  Am beginning to understand why architects get 20% of the cost of the house as their fee.  Weather cleared at noon (as forecast) into a gorgeous Saturday, with just enough breeze to blow the black flies away.  Spent a few hours cutting and bending the rebar that will be used to reinforce the sauna building footers.  As always, an excellent upper body workout… and this time there was no snow coming down to make the exercise even more interesting.  (Refer to the blog posting for 28 April 2010.)  To round out the day, put in 12″ offset stakes to mark the corners of the sauna building (we are getting just tooooo professional!) so that I can shovel some dirt tomorrow to create footer trenches at the desired elevation (that elevation being 5¾ inches below a mark that I’ve put on the wood walkway which, in theory, is where the southwest corner of the sauna building deck will join with the walkway).

9 May 2014

Forecast to be sort of a rainy, miserable day, so spent most of the morning doing detailed drawings to pinpoint where the footers need to be placed for the chimney and the two support posts for the steel I-beam that will support the middle of the house.  For a break from sitting, tackled smoothing out the driveway with the Kubota; the fill that was put in to even out the driveway slope was more than a little bony.  In the midst of that endeavor, Ceil Todd (neighbor across the street) brought over a couple of banana nut muffins hot out of the oven.  They went down real easy with some homemade chicken soup Lynne brought over the other day.  After two hours of grading, the driveway is much more passable (you’ll only lose one or two fillings driving over it), but still needs a couple of truckloads of crushed gravel to be right.  About 3:30 Larry Kaufmann (Long Ridge Concrete) arrived with a caravan driven by his two assistants, Kevin Clark and Victor Fifield.  The two helpers spent some quality time unloading concrete forms while Larry and I supervised reviewed the plan of attack for next week. By 4:15 they were gone, leaving me Long Ridge’s rebar cutter / bender so I can get some good exercise this weekend.  Went back to drawing… determining where the two Lower Level toilets and shower drain will be located with respect to the foundation wall sill plates, as that plumbing and the main waste line have to be roughed in before the cellar slab is poured.  Plus the main waste line has to penetrate the west side frost wall at some elevation en route to the septic tank.  Somehow they forgot to teach me all these things in college…

8 May 2014

Jimmy was back at 0745.  Wink delivered a dump truck load of sand shortly before 8, which Jimmy used to smooth the cellar area where the wall footers will be laid.  Then Jimmy started digging the trench for the frost wall that will support the west side of the house.  While that was ongoing, I went over to Kate’s to check email and put in an online order.  Just as I started the latter activity, the touchpad mouse on my (not-so) trusty laptop computer stopped working.  Nothing I could think to do would rectify the problem.  Gaack!  Headed into Middlebury (was out of ice cream, AGAIN!!!!), stopped to reassure the Goodro Lumber staff that I would be putting all their kids through college this summer, then went to CSI, a computer repair place I’d heard good things about.  The denizen of that emporium asked, “Is the touchpad turned on?”  To which I replied, “I didn’t know you could turn it off.”  So he pressed the F5 key and (1) the touchpad mouse started working again just fine and (2) my face turned bright red.  Got back to Fern Lake about 11, just as Jimmy was packing up from finishing this phase of his site work responsibilities.  After he left, went into Brandon to do more errands.  Then started cleaning up chunks of roots and some stumps that didn’t make it onto the truck on Tuesday.  Met Sean headed in as I was headed out the driveway with the first load.  We reviewed progress and the short-term schedule for an hour.  Then I finished the site cleanup, greased the poor tractor, and washed the mud and the blood and the gore off that much-abused machine.  Black flies still are well and truly present.

7 May 2014

Jimmy and Wink Rhodes (Ploof Excavating’s driver, loader operator, and man about town) started work at 0730.  Wink spent the morning hauling loader bucket after loader bucket of “extra” gravel from the house site to fill in the dip in our driveway.  The driveway now has a nice even, and much more benign, pitch for the first 200 feet.  Jimmy continued digging his way towards China.  Tammy, Nate, and Mary came at 0830 to recommence work on the sauna building site retaining wall.  The four of us had the wall complete, the sauna’s French drain installed, and the Kubota safely returned to its garage by 3:30.  Jimmy finally quit for the day at 6:30.  Black flies were pretty miserable in the afternoon.

 

6 May 2014

Dolores drank another 11 gallons of propane again today.  Temps still are getting down into the 30’s at night, so the furnace has been running a lot.  Jimmy arrived at 0730 and sent three large dump truck loads of stumps off to the landfill.  Tammy Walsh, Nathan Clert (Tammy’s nephew and assistant rock wall builder), and Mary Stockwell (no relation, but also a hard-working builder with rocks) all arrived just after 8.  The four of us proceeded to tackle the sauna building site retaining wall, with occasional help from Jimmy, who delivered and set several multi-ton rocks that were way beyond the Kubota’s capacity.  Knowing our relative abilities, Tammy operated the tractor all day while I helped with the manual labor side of things.  Sean arrived late morning and he, Jimmy, and I took a look at the accuracy of the nail I put in the hemlock by the car turnaround area ages ago, which theoretically represented the top of the  house cellar concrete walls.  After a fair bit of deliberation, we decided that the nail (and thus the house) was 10 inches too low.  Adjustment made, Jimmy went back to making big holes in the ground and even bigger piles of dirt.  By 4 o’clock (when Tammy and crew had to leave) about ⅞ of the sauna building retaining wall was built.  I then took over the reins of the tractor to remove excess dirt from the site.  Was just finishing up that work shortly before 6 when I got just a little too close to the soft bank I was working near… and the Kubota came within a whisker of rolling over, which would have done terrible things to (1) the tractor, (2) the wood walkway and halfway bench, (3) Fern Lake, and (4) my marriage.  Tried to extricate the tractor using the backhoe boom… but just made things worse and worse and worse.  On the brink of total disaster, left “I’ve got an emergency and I need you back here right now” voicemails with Sean and every number I could find for Jimmy.  Sean called back in short order, recommending that I secure the Kubota to a big tree, which I did using my biggest logging chain and come-along. Jimmy sent me a text message saying he was on his way.  He arrived, driving his front end loader (needed for tomorrow’s agenda) at 6:45.  We walked down to the scene of the crime, whereupon he said, “Would you mind if I try something?”  To which I replied, “Not at all, but be VERY careful!” Whereupon Jimmy (using the backhoe controls) and I (keeping tension on the logging chain with the come-along and operating (by hand) the foot pedal that makes the tractor go in reverse, slowly pulled / drove the tractor back up onto level ground.  PFM on Jimmy’s part; the guy is an absolute wizard!!!! James arrived just as we declared mission accomplished.  Right after Jimmy and James left at 7 (note the arrival / departure time differential!), Sean and Luther Corcoran (Sean’s other foreman) arrived. With the panic now abated, we three adjourned to Dolores for a liquid dinner. 





5 May 2014

 
Eagerly anticipating today’s milestone event, was dressed in my work duds and out the door at 0700.  Still very lonely two hours later, called Sean to see if maybe (sic) there had been a change in plans.  Got the text message (sent hours earlier) a few minutes later (thanks for nothing, Verizon Wireless), informing me that Jimmy Ploof wouldn’t be available until about noon. Jimmy arrived just after 11, and in an absolutely amazing display of excavator expertise, completely de-stumped the house site in just over an hour of frenetic digging.  The size stump that took me 5 hours with the Kubota to claw out down at the sauna site took Jimmy less than a minute to unearth.  Even with all that raw power, I swear he could have picked up a sheet of paper with his excavator… without wrinkling it!  Sean arrived, in company with his brother (and foreman) Ben, just as Jimmy was finishing the stump removal, which made quite a large pile. With Ben doing the photographer honors, Sean, Jimmy, and I posed for the obligatory ground-breaking ceremony picture.  Somehow the gold plating seems to have worn off my shovel.  After Jimmy left to retrieve his truck from the tire repair shop (which is why he was late arriving this morning), Sean, Ben, and I spent a couple of hours going over administrative and house specification issues.  Spent the next couple of hours coaxing electrons into patterns consistent with what Sean and I had decided.  Jimmy arrived back, with his son, James, at 4:30.  The three of us then spent an hour accurately staking out the house corners, then putting in ten-foot offset stakes so that Jimmy will know where to dig for the foundation tomorrow.