3 May 2011
Forecast was for heavy rain and a flood watch for this afternoon, so Liam Powers took a rain check on installing the shed electrical lights and power. Was at work by 6:45, getting the last course on the between-column walls that are exposed to the weather (under where the driveway will be). Now all the east and south side walls are ready for concrete reinforcement. Wore my rain jacket out to continue work after lunch. I’ll take full credit that it rained not a drop all afternoon. Got an additional course on three sections of the west wall… and had done all I could for the day by 4:15.