6 January 2016
Andy
Tracy arrived just before 8 with two of his workers, Tom Hobbs and Logan
Marsano. We spent an hour reviewing
where all the ductwork will be installed, then I left for an appointment in
Middlebury. Andy had departed by the
time I returned to Fern Lake at 11:30.
Logan left mid-afternoon to build air boxes in the Boot Hill Metal Bending
shop while Tom continued cutting holes in the main level floor through which
the air conditioning ducts will run.
Somehow it seems a bit strange to be installing the air conditioning
before installing the heating when the temperature is well below freezing
outside. As Tom was leaving just before
sunset, he discovered that The Granite Group’s truck had visited sometime this
afternoon and left $3,800 worth of plumbing and heating commodities on the
ground outside the garage. Needless to
say, we moved the lot inside before Tom left.