Tom
Hobbs and Logan arrived at 7:30 bearing a gift: the Venmar AVS E15 heat
recovery ventilation (HRV) unit, which, though cute and small, doesn’t stop it
from being quite expensive. The guys
spent the day running / connecting / insulating duct work. Mid-morning the First Corporation 8VMB air
handler unit was delivered. That’s where
the air conditioning (cold air) will come from during the two weeks in August
that it is needed here in Vermont and also where hot air can be generated
should the radiant floor heating need supplementing. Mr. Jonsered and I had to have a serious talk
with a tree that snapped off during yesterday’s winds and fell across the
driveway. Tom Morrisey arrived at 8:15
and we spent the day putting up and wiring ceiling boxes in the living / dining
room, kitchen, upper hall, master bedroom, and walk thru closet. Many decisions on the fly about where lights
will be installed. Somehow things look
different in the flesh than they do on paper… Ran out of boxes late afternoon.