29 August 2012
Back to Virginia in
just on 9 hours with a stop at Giddings Manufacturing and Equipment in Pittsford
to order a new driveway sign. The tire
inflation warning light came on again a mile down the road from Fern Lake,
stayed on for the next 507 miles, then went back out as I turned onto Newington
Forest Avenue, a ½ mile from the house.
Go figure!!!! Saw the extent of
Chree’s tripping-over-Shlomo injuries upon arrival home. Let’s just say that it’s a good thing I’ve
got witnesses to prove I was in Vermont last Friday, otherwise there would be a
restraining order issued in record time.
28 August 2012
27 August 2012
26 August 2012
25 August 2012
24 August 2012
Did errands with / for
Alverta in Burlington all morning.
Returned to Fern Lake at 2:30 and promptly got back to work on the
walkway took a nap. Awhile later, somewhat refreshed, dug the last hole for
and buried the remaining two in-ground posts needed to support the third
landing. Was admiring my handiwork and
doing a last measurement check when I realized that all of the posts are in the
wrong place due to very poor prior planning on the part of this Perkins. Shortly
thereafter, while in the lake soothing my bruised foot and the footprint-shaped
bruise on my butt, Chree called to let me know about her day in the emergency
room caused by a cute little black doggie, name of Shlomo, over whom she
tripped while walking said doggie this morning.
When retrieving a bottle of wine for dinner from the man cave, found a
pile of “sawdust” on the shed footer right under one of the oak beams… a beam
that I treated especially thoroughly with the BoraCare spray. On a positive note, dinner at Marty &
Merry’s was delicious as always… and somehow my wine glass was never empty
after regaling them with tales of the goings on over the last 24 hours. After
dark we all came up the hill to admire the walkway all lit up. In spite of the rocky, root-infested terrain
and elevated BAC, none of us ended up in an emergency room…
23 August 2012
Delivered mouse #3 to the Silver Lake parking lot hollow tree stump. Afterwards, spent an hour uploading 2½ weeks of blog postings to the fernlake.blogspot.com website. Then put the toe caps on the third walkway section. That means that 158 feet of the walkway now are complete. Only 274 more feet to go! Started work on putting in the four in-ground posts that will support the third landing. Placement of the first two was very fussy… they have to be in exactly the right position (including height above ground) for both the landing construction and the start of the next walkway section. Got that done and was about to plant the third in-ground post when a call from Lynne sent me to Burlington for the night to assist Alverta, who was experiencing her first ever ambulance ride as Lynne and I were speaking and, ultimately, again needed rescuing from the clutches of the Fletcher Allen emergency room.
22 August 2012
Finished putting deck
boards on the third section of walkway, then installed the railing caps and
railing for that section. Things go a
lot faster when there aren’t any funky bends in the middle of the straightaway. FINALLY found the picture editing / compression
program needed to shrink my .jpg files down to web-compatible size. Turned out to be a MS Office, not a Windows
7, program. Once I figured that out, was
a matter of minutes to load it onto the laptop from my Office 2007 CD. Captured yet another mouse in the utensils
drawer trap.
21 August 2012
20 August 2012
19 August 2012
Had to fire up the RV
furnace to take the chill off while having breakfast this morning. Isn’t this August, the only WARM month in
Vermont???? Spent most of the morning
scrubbing and buffing, making Delores and her environs ready for guests. Alverta and Lynne arrived at 11:30, a full
hour before I was expecting them. With some frenzied activity, got the
remaining preps done while trying to be a semi-attentive host. Lunch was served promptly at 1. Jake arrived as we were finishing our repast…
and in short order inhaled nearly as much food and drink as the three of us had
already put down our gullets. Perry
arrived (not hungry) as the four of us were finishing dessert. While Perry, Jake, and I sat around the
campfire talking about walkway engineering, the two ladies retired to the RV
and apparently spent some quality time “evening up the edge” of the still-warm
walnut-infused Ghirardelli chocolate brownies.
Least wise the baking dish was a lot less full than I remembered when
time came to put the brownies under wrap.
Guests departed at 3, a few minutes before Merry and Graham came up the
hill for a walkway tour (and to distract me from attacking the awaiting kitchen
calamity). After the dishes were done,
the rest of the day and evening was spent doing financial analysis for
Alverta. Have I mentioned yet how much I
dislike the #$@!%^! “new and improved” touchpad mouse on my new laptop?
18 August 2012
Installed the
in-ground posts that form the transition from the walkway to the third landing.
Skipped to the end of this section because the critical measurements for the
longitudinals are from the second landing south to the first two sets of
in-ground posts and from the third landing north to the last two sets of
in-ground posts. There will be four sets of in-ground posts in this section,
with the distance between the second and third sets a non-standard distance
(should be 4′ 6″) because of where the third landing has to be to set up for
the next section. Sounds more
complicated than it is… which is not to say that I won’t find a way to screw it
up somehow, like forgetting that my tape was reading 1″ short when I measured
for one of the posts this morning, so had to dig it back up and start anew
after I had positioned it perfectly, just in the wrong spot. And, yes, a 1″ positioning error would have
significantly messed up the alignment of the third landing. And, yes, when I put a post in the ground,
it’s meant to stay there forever… digging it back up was a real female dog.
Mid-morning Marty came over to request assistance with an urgent plumbing
problem. Fortunately Perry has virtually every tool ever invented and the
vicegrip with chain device (used for rotating threaded pipe) that he lent us
proved to be exactly what was needed to solve the problem. Was just thinking to myself that the
in-ground posts in this section were going in nice and easy (mostly grey and
yellow sand with only a few small rocks and very manageable roots) when I went
down six inches (okay, maybe it was only four and a half…) and hit the big one,
which, of course, was imbedded at an inclined angle. After probing all around, determined that
that critter weren’t coming out of the ground without some serious heavy
equipment. So fired up the Skilsaw with diamond tipped blade and promptly
stalled the generator (forgot to flip the switch that keeps it revved up so
that it can handle a sudden large current draw… like trying to cut rock). Once the rock had a nice level platform
carved into it, tried to drill a ½″ diameter anchor hole with the hammer drill,
thinking that this rock looked a bit softer than the granite I failed to drill
a month ago. After beating myself and the drill to death for 10 minutes I had
achieved a ½″ cavity (okay, maybe it was only four and a half millimeters) and
gave that idea up as a lost cause.
17 August 2012
16 August 2012
15 August 2012
Must have misunderstood the NOAA weather people when they said there was a 70% chance of rain today, ‘cause it was a beautiful day for working. Put in the other two in-ground / railing posts that define the west side of the second landing, then installed the landing light and the framework for the deck boards. Late afternoon, Tammy Walsh and Bob LaPorte (who are working together to repair a portion of Marty & Merry’s driveway) came up to admire the walkway and sample my beer supply. Got the new laptop semi-setup and spent most of the evening catching up with the blog and swearing profusely at the #$@!%#@!!! mouse touch-pad that seems to want to do everything but move the mouse pointer to where I want it in the document.
14 August 2012
Another adventuresome
bike ride with Marty. Details withheld in deference to the sensibilities of the
viewing audience. Installed the walkway deck boards for the last four feet down
to the start of the second landing. The
final board ended up exactly where it was supposed to be, i.e., I did
put the final in-ground posts for this section in the right place. Went into
Burlington after lunch to pick up my new computer from Best Buy where the Geek
Squad folks were able to retrieve and transfer all of the data from my dead
computer to the new one.
13 August 2012
12 August 2012
Mouse (mice?) turned
up its pointy little nose(s) at the honey roasted peanuts. Spent the first two hours of the morning
undoing yesterday afternoon’s work on the walkway, fixing the railing post
alignment problem and putting everything back together again. This is exactly
why the walkway is being put together with bolts and screws, not nails. After that, carried on with installing deck
boards, railing caps, and railings sown to as far as I’ve built (4′ 6″ from the
second landing). Ripped toe cap boards
from some really junky “used but good” 2x6’s – stalling (overheating) the
radial arm saw motor twice in the process. Time to get that blade
resharpened… Went kayaking at dusk
hoping to see some the Perseid meteor shower.
No joy on that, but did see one meteor that was the biggest, brightest
I’ve ever seen!
11 August 2012
Reset the last set of
stringers I installed day before yesterday – my slope jig said the walkway was
getting shallower than the 1 in 7.5 desired pitch. Moved a 375 lb rock that was right in the way
of the next in-ground post. Ran out of
dirt for backfilling the post holes ‘cause of all the extraneous granite that
has been removed from the holes, so had to scavenge a couple of wheelbarrow
loads of gravel from Tammy’s dredged spoils pile. Installed the next set of
in-ground posts, stringers, railing post, and longitudinals. Started to rain right after lunch, so spent
two hours repairing and reinstalling the RV bedroom blind. Then put deck boards on the walkway for a
couple of hours and realized that I’ve screwed up the placement of the last
railing post (which guides the placement of the deck boards) so all the
post-rain work will have to be undone then redone. Oh, joy!
Mouse (mice?) is back – another wine cork discovered chewed in the
utensil drawer. Set up a trap with honey
roasted peanuts this time.
10 August 2012
To Burlington to buy a
new laptop computer – a Toshiba Satellite C855-S5206, with way more capacity
and capabilities than this fading boomer will ever use. Hopefully the Best Buy Geek Squad will be
able to recover all the data off the dead laptop and move it over to the new
one. If not, then I’ll just have to
drown my sorrows with Scotch and then drown my sorry butt in the lake… the last
resort for idiots who don’t back up their files! Did five loads of laundry at Alverta’s…
somebody has been a very dirty boy.
9 August 2012
8 August 2012
7 August 2012
After a totally sleepless night, Marty and I did our usual 10 miles, then I went to work installing the longitudinal and deck boards for the next 12′ of the walkway. Moved the ramp / walkway connection point “out” 1½″ so that the first deck board would be in the right position. Moved a beautiful 1,000 pound rock (5′ long x 14″ square) out of the way of where the next set of in-ground posts need to go. That baby (and its sister, that didn’t have to be moved) will make fine capstones on a future retaining wall. Proving that I’m getting too strong for my own good: broke one of my Irwin Quick Clamps… which takes some doing! Another delicious, delightful dinner at Marty & Merry’s.
6 August 2012
Called Goodro Lumber at
7:30 and was told that their truck was being loaded, soon to be headed my
way. So called Marty and took a rain
check on our oft-postponed first-since-the-crash bike ride. The Goodro truck showed up at 9, long after
we would have returned from bicycling.
You know what would have happened had I headed out with Marty at 8… As soon as the Goodro truck departed, called
McDonough’s in Brandon about getting the Ranger tire repaired. Was told to be there at 9:45, so put 40 psi
of air in the right rear flat tire and drove as fast as I dared into Brandon,
arriving at the service station 15 minutes later with 20 psi left in the
tire. Whew!!!! Unfortunately, as soon as Mike McDonough saw
the gash in the tire’s inside sidewall he said, “Unrepairable!”. But then he told me about Brandon Auto
Salvage on Route 7 in Leicester, a place I’ve driven past a zillion times and
never paid any attention. They have
scads of “used but good” tires taken off wrecked cars and trucks. Sure enough, a very nice used (but in better
shape than the other three tires on the truck) 235 75R15 tire was just begging
to be put on the Ranger, which was soon done… for a grand total of $65 (tire,
mounting, spin balancing, and old tire disposal all included). Now that’s a good deal!!!! After getting water at Lynne & Perry’s,
was back to Fern Lake by 11:30. With
time in hand before lunch, built a small ramp for the generator to sit level on
as I move it incrementally down the wooden walkway. After lunch, sawed a 25° angle the length of
a 4x6 post, then dug the holes and planted that post plus two 4x4 posts that,
together, form this slight turn in the walkway.
Then discovered that I will need 4½″ lag screws (vice the hundreds of 6″
lag screws that I have) to attach stringers to those particular posts. So dug the holes for the next two in-ground
posts, one of which will have to be wedged into a wide crack in an enormous
rock, then called it a day. And in other good news: by throwing my laptop violently
to the ground last night, a months-long problem with the computer’s video
display has been fixed. Somebody please
explain that one to me… DISASTER!!!! When next I went to use my computer there
was a zzzzzt sound, the smell of frying electronics, the
finally-working-right-video display went black, and the computer became
completely nonfunctional. Was is just
the video display that fried or was it the motherboard? News in a week… The wise turtle would have
been backing up all his files on a regular basis just in case his computer got
sick. The smart turtle would have backed up all his irreplaceable data when the
computer did get sick. Guess who’s neither smart nor wise???? Guess who’s sweating bullets right now????
5 August 2012
With all modesty aside, I do make an excellent, and oft requested, breakfast omelet. Except for this morning when Alex asked for some of the leftover BBG chicken in his creation and I foolishly tried to heat it up a bit in my only frying pan. The BBQ sauce promptly stuck to the pan which meant that the “omelets” stuck semi-permanently to the BBQ sauce and, consequently, became a hodgepodge of ingredients with some bits of egg mixed in. We all cleaned our plates, so, though unsightly, the concoctions were still tasty enough. The stump / brush fire was still smoldering when we finally ventured forth. So Alex returned to fire tending while Katy and I went blackberry picking… which was the first time in her life that Katy has ever been berry picking. Apparently that’s not one of the available options when you grow up in Houston, Texas. We got a couple of quarts, and many scratches, in not much time, and didn’t even begin to deplete the stock in our patch out by Route 53. Then Katy and I went canoeing while Alex encouraged the last remaining stump (the one the Ranger had had such a hard time towing into position) to become charcoal. Katy & Alex headed back to Boston at 2… in the midst of an hour –long rainstorm. I spent the afternoon making lasagna, swimming, and generally relaxing. While over at Kate & Dan’s catching up on the blog postings another rainstorm started to arrive, so took shelter in their woodshed while trying to get the last little bit done and the email sent out. Slipped and my laptop computer went flying. Still works, obviously, but the cover no longer closes properly ‘cause one of the hinges is somewhat beyond broken.
4 August 2012
Let the record show that Katy did say, at least five minutes before calamity struck, “Doug, I think this is a bad idea!” But that’s getting ahead of the story. Katy and Alex arrived just before midnight, as expected, except that I had fallen asleep on the dinette settee that makes into a bed, and failed to hear them arrive. Consequently, we somewhat surprised each other as they came though the main cabin door. After dragging them out to see the walkway all lit up, we retired. Early this morning Alex and I arose and Katy was induced to crawl out of bed. After a quick breakfast, Alex got to indulge his pyromaniac fantasies while Katy and I used the Ranger to drag load after load of brush from the woods over to the bonfire site. Having removed all the readily accessible brush piles by 11 o’clock, I figured I could snake the Ranger down the hill a bit further to retrieve a collection of limbs that were a long trudge from the lower “driveway”. That’s when Katy let me know her opinion of the idea, forthrightly and directly. Being overconfident and stupid, I ignored her advice until she yelled, “You’re on a rock!”, and the Ranger stopped moving. “On” a rock was hardly an apt description. I had backed up over an 850 pound (by later measurement) Leicester nugget and the truck suspension (and later the driveshaft) were firmly joined to granite. That truck weren’t going nowhere without some serious machinations… which took the next four hours and every word in my sailor’s vocabulary (uttered silently, of course, in deference to a young lady’s sensibilities). Have you ever had a truck fall off a jack while you were underneath it? Katy yelled in the nick of time and then learned that, although her father-in-law is 62 years old, he can move with alacrity then properly motivated. Wouldn’t have been so bad if the truck had toppled sidewise just once, but it happened four times as we raised the rear end, laboriously, using two jacks and makeshift cribbing, into the air so that the critical underside components were high enough to drag the rock out from underneath the truck. In the process “we” (I seem to have gotten a mouse in my pocket while crawling around in the dirt) managed to poke a hole in the right rear tire. Once again, Chris Thiel’s air compressor saved the bacon, as we could inflate the tire (very temporarily) when it came time to finally drive the Ranger away from the disaster site. Then it was time to prepare ourselves (lake cool-down followed by cleansing shower), campfire, and food (BBQ chicken, homemade baked beans infused with campfire cooked hot dogs, Kingsley’s corn, garden salad, brownies right out of the oven topped with Ben & Jerry’s Vanilla Heath Bar Crunch) for the arrival of Marty & Merry (bearing gifts (plural) of wine that somehow all disappeared before a most delightful evening was adjourned. After dark, Katy (lookout), Alex and I took Hopea Kanootti for a spin around the lake. When we returned dockside, Katy and Alex most generously tackled the voluminous dinner dishes while I enjoyed, yet again, the calming waters of Fern Lake.
3 August 2012
Awoke this morning
thinking of joints. No, not that kind of
joint! I’m talking about the connection
between two pieces of wood, specifically the longitudinals for the wooden walkway. Decided that, for maximum strength, I need to
have the lap joints fall either on (ideally) or close to the stringers that
support the longitudinals, which are spaced eight feet apart. So called Goodro’s first thing they opened
and offered to trade them sixteen 2x4x12’s for twelve 2x4x16’s (works out to
the same number of board feet of lumber).
Delivery expected Monday. Have I
ever mentioned that Perry is not only a fabulous chef, but also a brilliant
carpenter? He suggested coating the lag
bolt threads with bar soap (he uses Ivory, but all I have is Dial). Drove beaucoup lag bolts today and broke only
the one I didn’t soap! Installed
the next pair of in-ground posts (one of which had to go exactly where a LARGE
rock used to reside, until Tammy moved it out of the way with her backhoe), two
sets of stringers, and their associated railing posts. Surveyed (alignment only; elevations to
follow) the next two sections of the walkway path, as the walkway needs to veer
west 25 degrees in another four feet or people will knock their heads on a very nice, but
very hard, cherry tree that is leaning just a tad too much downhill. Can’t have that… Then, once past the cherry tree, the walkway
needs to make a precise 90 degree left turn, passing just so between a large oak and a
small beech. Trimmed the driveway
vegetation just before diving in the lake.
I’m sure Alex and Katy will be mightily impressed with the manicured
weeds when they arrive at midnight.
2 August 2012
1 August 2012
NOAA Weather Radio said today was supposed to be partly-sunny deteriorating into thunderstorms and rain in the afternoon / evening. Woke up to total overcast and five minutes of a rain shower at 5 minutes to 8… just in time to cancel Marty and my inaugural post-crash bike ride. So worked in the shed all morning fabricating an 8½′ long by 3′ wide ramp (made entirely out of wood otherwise destined for the burn pile) to transition from the lower “driveway” surface up onto the wooden walkway… whose deck is some 15″ above the current ground level. The ramp just sits (very securely) on the end of the walkway, so it can easily (if you’re very strong… or have a helper) be moved out of the way when vehicles need to get through that area. Needless to say, getting the ramp single-handedly from the fabrication site to the installation site was a bit of a challenge, especially negotiating the 120° turn at the first landing. By the time that was accomplished the skies were, indeed, partly-sunny. So set to work digging holes for the next set of in-ground posts. Got the posts in fine, but, when I broke the fifth ¼″ lag bolt trying to attach the stringers, I called it a day. The problem is either: (a) I’ve gotten too strong for my own good, (b) the 3/16 drill bit I’m using for the pilot holes is just a tad too small, (c) the 20+ year old 4x4 posts I’m reusing from the old stairway are just too dry and tough, (d) they’re using really inferior steel to make lag bolts these days, or (e) all of the above. Ate a whole can of spinach (3½ servings if you can believe the label) with dinner tonight. Those lag bolts won’t have a prayer tomorrow…
Subscribe to:
Posts (Atom)