29 August 2012

Back to Virginia in just on 9 hours with a stop at Giddings Manufacturing and Equipment in Pittsford to order a new driveway sign.  The tire inflation warning light came on again a mile down the road from Fern Lake, stayed on for the next 507 miles, then went back out as I turned onto Newington Forest Avenue, a ½ mile from the house.  Go figure!!!!  Saw the extent of Chree’s tripping-over-Shlomo injuries upon arrival home.  Let’s just say that it’s a good thing I’ve got witnesses to prove I was in Vermont last Friday, otherwise there would be a restraining order issued in record time.

28 August 2012

 
Called my Virginia mechanic yesterday to make an appointment for the Sienna later this week.  After over a month illuminating every time I drove the van, on the way to / from the Salisbury library today the tire inflation warning light did NOT come on.  At least the Check Engine light is still lit… for now.  After rain off and on all night, the weather still was very unsettled this morning, so kept tools mostly under cover and worked on loading the van with anything I don’t think I’ll need between now and the end of the construction season (…and we all know how that is going to work out!), preparing the site for a week’s absence, and creating more footers, stringers, and railing posts.  During lunch the sun came out and the skies started to clear… just as forecast.  Hauled all my tools (seems like literally) down to the end of the walkway and started attaching stringers to the in-ground posts I put in yesterday.  No sooner was the first one done when a thunderstorm came rolling in out of nowhere, necessitating a frantic scramble to get at least the electrical tools covered up again.  By the time I finally sought shelter in the RV, was more than a little damp around the edges.  A half hour later the skies cleared again, but by then it was time for the library run… apparently on four good tires.  Returned to Fern Lake just before 3, finished putting on the stringers, the associated railing posts, and getting everything put away and secured.  In case you were wondering, the lake temperature is still a lovely 79 degrees.

27 August 2012

 
Forecast was for deteriorating weather as the day went on, with rain likely tonight.  Didn’t want to have electrically-powered tools lying about if the rain came early, so spent the day digging holes and planting the next four sets of in-ground posts. Only two brief rain showers while I was working this afternoon and a third just as I was getting changed for my cool down / clean up plunge in the lake.

26 August 2012

 
After the usual 10 mile bike ride with Marty, intended to get the deck boards on the third landing.  Found out right away that the radial arm saw will crosscut a maximum of 60 degrees and a wee bit.  The first angle to be cut was 69°, which meant having to use the Skilsaw. Uttering a discouraging word (though the skies were sunny all day…), I loaded the generator and Sawzall into the Ranger and tried to shorten the driveway signpost by ¼″ so the mounting bracket holes would line up better… something I’ve had on the to do list for some considerable time.  Found out (after ruining two metal cutting blades) that the steel in that signpost is some tough stuff.  Tried using my hacksaw with a new blade, but it quickly became apparent that the signpost was cutting the blade and not vice versa.  Gave up and tackled to do list item #2: removing the “floor” of the RV generator compartment so that I can lower it 3″ using the expensive channel steel that I got from Lou Nop last week.  Using my last metal cutting blade, the Sawzall made short work of four of the totally rusted bolts holding the compartment floor in place.  Unfortunately, the fifth (last) bolt was in a position where I couldn’t get at it with the Sawzall.  Merde, as they say, alors (if you’ll pardon my French)!!!! Tried a cold chisel, but quickly gave that up as a hopeless approach.  Then remembered that I do have a diamond-tipped blade for the Skilsaw… and diamond is pretty tough stuff so maybe…  (Can you see the light bulb glowing dimly????)  Worked like a champ!  Ate an early lunch, then dragged the generator, Skilsaw (restored to wood cutting mode), sawhorses, and seemingly every other tool I own down to the third landing worksite.  Other than the cuts not being nearly as pretty as when done on the radial arm saw, cutting the deck boards for the landing on site was a lot easier than I was expecting… and certainly saved countless trips up and down and up and down the walkway.  Got the landing finished at 3 o’clock, put away tools, hopped in the lake to cool off, did two days worth of dishes, shaved and showered, and was at Lynne & Perry’s by two minutes to four.  That’s what you call gettin’ ‘er done!  The three of us then went over to Camp Songadeewin (the Keywaydin girls camp) for the annual Lake Dunmore / Fern Lake Association picnic.  Burgers and dogs, great potato salad, plenty of beer and cheap wine, but not nearly enough soda considering it was well north of 80° and downright h•o•t out in the sun.  The new dining hall is, as advertised, gorgeous post and beam construction… and VERY noisy with a hundred or so people trying to hold a conversation inside.

25 August 2012

 
Keeping the string of no emergency room visits going, Marty and I did our first PC2 bike ride… 10 miles around the Neshobe Golf Course loop.  Ended up moving three of the four posts for the third landing.  Needless to say, the one that had to move the least distance was the one that was the most difficult to get back in the ground properly positioned.  Got back to where I started by lunchtime.  In the afternoon installed all the framing for the third landing, then put up the landing light.

24 August 2012

Did errands with / for Alverta in Burlington all morning.  Returned to Fern Lake at 2:30 and promptly got back to work on the walkway took a nap. Awhile later, somewhat refreshed, dug the last hole for and buried the remaining two in-ground posts needed to support the third landing.  Was admiring my handiwork and doing a last measurement check when I realized that all of the posts are in the wrong place due to very poor prior planning on the part of this Perkins. Shortly thereafter, while in the lake soothing my bruised foot and the footprint-shaped bruise on my butt, Chree called to let me know about her day in the emergency room caused by a cute little black doggie, name of Shlomo, over whom she tripped while walking said doggie this morning.  When retrieving a bottle of wine for dinner from the man cave, found a pile of “sawdust” on the shed footer right under one of the oak beams… a beam that I treated especially thoroughly with the BoraCare spray.  On a positive note, dinner at Marty & Merry’s was delicious as always… and somehow my wine glass was never empty after regaling them with tales of the goings on over the last 24 hours. After dark we all came up the hill to admire the walkway all lit up.  In spite of the rocky, root-infested terrain and elevated BAC, none of us ended up in an emergency room…

23 August 2012


Delivered mouse #3 to the Silver Lake parking lot hollow tree stump.  Afterwards, spent an hour uploading 2½ weeks of blog postings to the fernlake.blogspot.com website.  Then put the toe caps on the third walkway section.  That means that 158 feet of the walkway now are complete.  Only 274 more feet to go!  Started work on putting in the four in-ground posts that will support the third landing.  Placement of the first two was very fussy… they have to be in exactly the right position (including height above ground) for both the landing construction and the start of the next walkway section.  Got that done and was about to plant the third in-ground post when a call from Lynne sent me to Burlington for the night to assist Alverta, who was experiencing her first ever ambulance ride as Lynne and I were speaking and, ultimately, again needed rescuing from the clutches of the Fletcher Allen emergency room.

22 August 2012

Finished putting deck boards on the third section of walkway, then installed the railing caps and railing for that section.  Things go a lot faster when there aren’t any funky bends in the middle of the straightaway.  FINALLY found the picture editing / compression program needed to shrink my .jpg files down to web-compatible size.  Turned out to be a MS Office, not a Windows 7, program.  Once I figured that out, was a matter of minutes to load it onto the laptop from my Office 2007 CD.  Captured yet another mouse in the utensils drawer trap.

21 August 2012

 
Spent a couple of hours cutting 5/4x6x12 pressure treated deck boards into 3′ lengths and schlepping them down to the end of the yellow brick road completed wooden walkway. Then into Burlington I went to deliver a college beer refrigerator being donated by Lynne & Perry to Lindsey, Steve’s younger daughter.  Stopped at Best Buy to inquire about the picture editing / compressing software that is MIA.  The Geek Squad were, again, less than no help (two different people blew clouds of smoke up you know where… and even I, no computer expert, could tell they were just making something up to get rid of me). In passing, one of them said they get a lot of complaints about the touchpad on the latest Toshiba laptops. Would have been nice if the salesperson had mentioned that little tidbit when I was looking at replacement computers. Also spent some time with Alverta reviewing the financial impacts of alternative living arrangements she is considering. Check Engine light came on (in the Sienna this time) as I was headed north.  Looks kinda pretty next to the tire inflation warning light that has been on for a month… with the tires (including spare) checked regularly for proper inflation. If it’s not one thing, it’s another… Back to Fern Lake by 4:30, whereupon I started putting deck boards on the walkway section between the second and third landings, getting about ⅓ completed before swim call.

20 August 2012

 
Don’t you hate it when it starts raining when you’re swimming?  Other than that minor complaint, a good day of work.  Installed the last three in-ground posts for the walkway section between the second and third landings, their associated stringers and railing posts, then put on the longitudinals and two of the lights.  All ready to start laying deck boards!  Tasi instructed me on how to access hidden file folders in Windows 7, so I finally could move my Outlook contact list file into the correct (hidden) folder so that Outlook could find it.  Life is good!!!!  Now if I can just find the file that lets me compress 5 MB photo files into a size more manageable for posting into the blog… 

19 August 2012

Had to fire up the RV furnace to take the chill off while having breakfast this morning.  Isn’t this August, the only WARM month in Vermont????  Spent most of the morning scrubbing and buffing, making Delores and her environs ready for guests.  Alverta and Lynne arrived at 11:30, a full hour before I was expecting them. With some frenzied activity, got the remaining preps done while trying to be a semi-attentive host.  Lunch was served promptly at 1.  Jake arrived as we were finishing our repast… and in short order inhaled nearly as much food and drink as the three of us had already put down our gullets.  Perry arrived (not hungry) as the four of us were finishing dessert.  While Perry, Jake, and I sat around the campfire talking about walkway engineering, the two ladies retired to the RV and apparently spent some quality time “evening up the edge” of the still-warm walnut-infused Ghirardelli chocolate brownies.  Least wise the baking dish was a lot less full than I remembered when time came to put the brownies under wrap.  Guests departed at 3, a few minutes before Merry and Graham came up the hill for a walkway tour (and to distract me from attacking the awaiting kitchen calamity).  After the dishes were done, the rest of the day and evening was spent doing financial analysis for Alverta.  Have I mentioned yet how much I dislike the #$@!%^! “new and improved” touchpad mouse on my new laptop?

18 August 2012

Installed the in-ground posts that form the transition from the walkway to the third landing. Skipped to the end of this section because the critical measurements for the longitudinals are from the second landing south to the first two sets of in-ground posts and from the third landing north to the last two sets of in-ground posts. There will be four sets of in-ground posts in this section, with the distance between the second and third sets a non-standard distance (should be 4′ 6″) because of where the third landing has to be to set up for the next section.  Sounds more complicated than it is… which is not to say that I won’t find a way to screw it up somehow, like forgetting that my tape was reading 1″ short when I measured for one of the posts this morning, so had to dig it back up and start anew after I had positioned it perfectly, just in the wrong spot.  And, yes, a 1″ positioning error would have significantly messed up the alignment of the third landing.  And, yes, when I put a post in the ground, it’s meant to stay there forever… digging it back up was a real female dog. Mid-morning Marty came over to request assistance with an urgent plumbing problem. Fortunately Perry has virtually every tool ever invented and the vicegrip with chain device (used for rotating threaded pipe) that he lent us proved to be exactly what was needed to solve the problem.  Was just thinking to myself that the in-ground posts in this section were going in nice and easy (mostly grey and yellow sand with only a few small rocks and very manageable roots) when I went down six inches (okay, maybe it was only four and a half…) and hit the big one, which, of course, was imbedded at an inclined angle.  After probing all around, determined that that critter weren’t coming out of the ground without some serious heavy equipment. So fired up the Skilsaw with diamond tipped blade and promptly stalled the generator (forgot to flip the switch that keeps it revved up so that it can handle a sudden large current draw… like trying to cut rock).  Once the rock had a nice level platform carved into it, tried to drill a ½″ diameter anchor hole with the hammer drill, thinking that this rock looked a bit softer than the granite I failed to drill a month ago. After beating myself and the drill to death for 10 minutes I had achieved a ½″ cavity (okay, maybe it was only four and a half millimeters) and gave that idea up as a lost cause.

17 August 2012

 
While dropping off many radial arm saw blades, my variable width dado (that hasn’t been sharpened in three decades), and the much abused brush saw at Ed Minor’s Saw Shop, found a new home for the mouse under a hollow stump on Shacklets Road… a couple of miles from here, and the other side of the lake to boot.  Called the Geek Squad no help center about the Outlook contact list. Will have to take the laptop back to South Burlington to have that little problem fixed. It’s only 100 miles and 2½ hours for the round trip… but real pretty views along US 7 and you do pass right by the Shelburne Farms Winery.  Hmmm… Surveyed the next section and discovered that the walkway will be a foot below grade level at the fourth landing, so the constant slope plan remains in effect, even though most of the section between the second and third landings will be 3 to 4 feet in the air.  Installed the next two sets of in-ground posts, stringers, and railing posts.  Threatened rain all afternoon, but didn’t start until just after I finished for the day.  Sometimes you just live right!  Finally finished transcribing the week’s worth of blog notes that were hand-written while I was sans computer.

16 August 2012

 
You know you’re having a really good day when every other word, typically uttered with some feeling and volume, starts with the letter F.  I mean, really, did I even cut one board correctly the first time today????  Started the day trying to get my Microsoft Outlook account set up again.  After an hour of frustration, could receive emails, the contact list remains blank (though I know the Geek Squad imported that file from the dead laptop), and I get an error message when trying to send an email.  Started work on putting the deck boards on the second landing.  Soon thereafter was visited by Marty and two of his grandchildren, Graham and Gabriella Glassner.  Installed the rest of the railing cap, railing, and toe cap, completing the first 122′ of the walkway.  Surveyed the next section (alignment and elevation).  Really don’t like how high off the ground that section is going to be… but can’t decide whether or not to abandon the constant slope plan.  In spite of the weather forecast for sunny skies all day, a thunderstorm rolled through at 3 o’clock, giving me an excuse to replenish my honey roasted peanuts supply in Brandon.  Dinner at Lynne & Perry’s – fabulous cuisine and over-the-top presentation, as always. There was another mouse in the trap when I returned to Fern Lake.  Doesn’t sound like he/she/it is enjoying the honey roasted peanuts as much as I do…  Tasi provided a phone consultation which fixed the Outlook outgoing message problem.  Still haven’t been able to figure out how to import the Outlook contact list file into the right place so that Outlook can access it.  The wise turtle completely backed up all of his laptop files onto an SD card… and then slept very soundly for the first time in a week.

15 August 2012


Must have misunderstood the NOAA weather people when they said there was a 70% chance of rain today, ‘cause it was a beautiful day for working.  Put in the other two in-ground / railing posts that define the west side of the second landing, then installed the landing light and the framework for the deck boards.  Late afternoon, Tammy Walsh and Bob LaPorte (who are working together to repair a portion of Marty & Merry’s driveway) came up to admire the walkway and sample my beer supply.  Got the new laptop semi-setup and spent most of the evening catching up with the blog and swearing profusely at the #$@!%#@!!! mouse touch-pad that seems to want to do everything but move the mouse pointer to where I want it in the document.

14 August 2012

Another adventuresome bike ride with Marty. Details withheld in deference to the sensibilities of the viewing audience. Installed the walkway deck boards for the last four feet down to the start of the second landing.  The final board ended up exactly where it was supposed to be, i.e., I did put the final in-ground posts for this section in the right place. Went into Burlington after lunch to pick up my new computer from Best Buy where the Geek Squad folks were able to retrieve and transfer all of the data from my dead computer to the new one.

13 August 2012

 
There was a mouse in the trap this morning!!!!  He/she/it now resides under a hollow stump in the Silver Lake parking lot – two miles from here.  Bike ride with Marty, per usual.  Then put toe caps on the section of walkway currently abuildin’.  Dug holes for then planted the in-ground posts that transition from the walkway to the second landing.  Southern post was right on top of a huge, unmovable-without-a-backhoe rock, so that post ain’t in the ground very deep.  For strength / stability, overcompensated on that post’s northern sister, whose butt end is halfway to China.  Fingers crossed that those two posts are within ¼″ of where they’re supposed to be for the walkway / landing transition.  Installed the stringers, railing post, and final pair of longitudinals for this section.  Surveyed the elevation from from the top of the walkway to the second landing – a distance of 122′ 9″.  With a 1 in 7.5 slope, that elevation change should be 16′ 4″.  Actual, as-built, elevation change: 16′ 1″.  Not too awful bad!!!!

12 August 2012

Mouse (mice?) turned up its pointy little nose(s) at the honey roasted peanuts.  Spent the first two hours of the morning undoing yesterday afternoon’s work on the walkway, fixing the railing post alignment problem and putting everything back together again. This is exactly why the walkway is being put together with bolts and screws, not nails.  After that, carried on with installing deck boards, railing caps, and railings sown to as far as I’ve built (4′ 6″ from the second landing).  Ripped toe cap boards from some really junky “used but good” 2x6’s – stalling (overheating) the radial arm saw motor twice in the process. Time to get that blade resharpened…  Went kayaking at dusk hoping to see some the Perseid meteor shower.  No joy on that, but did see one meteor that was the biggest, brightest I’ve ever seen!

11 August 2012

Reset the last set of stringers I installed day before yesterday – my slope jig said the walkway was getting shallower than the 1 in 7.5 desired pitch.  Moved a 375 lb rock that was right in the way of the next in-ground post.  Ran out of dirt for backfilling the post holes ‘cause of all the extraneous granite that has been removed from the holes, so had to scavenge a couple of wheelbarrow loads of gravel from Tammy’s dredged spoils pile. Installed the next set of in-ground posts, stringers, railing post, and longitudinals.   Started to rain right after lunch, so spent two hours repairing and reinstalling the RV bedroom blind.  Then put deck boards on the walkway for a couple of hours and realized that I’ve screwed up the placement of the last railing post (which guides the placement of the deck boards) so all the post-rain work will have to be undone then redone.  Oh, joy!  Mouse (mice?) is back – another wine cork discovered chewed in the utensil drawer.  Set up a trap with honey roasted peanuts this time.

10 August 2012

To Burlington to buy a new laptop computer – a Toshiba Satellite C855-S5206, with way more capacity and capabilities than this fading boomer will ever use.  Hopefully the Best Buy Geek Squad will be able to recover all the data off the dead laptop and move it over to the new one.  If not, then I’ll just have to drown my sorrows with Scotch and then drown my sorry butt in the lake… the last resort for idiots who don’t back up their files!  Did five loads of laundry at Alverta’s… somebody has been a very dirty boy.

9 August 2012

 
Again with the biking… Installed railing post caps, lights, and deck boards down to the 25° bend.  Picked a quart of blackberries for Lynne & Perry in less than ½ hour right after lunch.  Thundered and multiple gust fronts blew through all afternoon, but no rain until 5 o’clock quitting time.

8 August 2012

 
Another 10 miles of biking with Marty to start the day.  Put in the next set of in-ground posts, stringers, and railing post past the 25° bend.  Cut the four longitudinal for either side of the 25° bend.  Swam across the lake and back without stopping to rest on the west side (a first).

7 August 2012


After a totally sleepless night, Marty and I did our usual 10 miles, then I went to work installing the longitudinal and deck boards for the next 12′ of the walkway.  Moved the ramp / walkway connection point “out” 1½″ so that the first deck board would be in the right position.  Moved a beautiful 1,000 pound rock (5′ long x 14″ square) out of the way of where the next set of in-ground posts need to go.  That baby (and its sister, that didn’t have to be moved) will make fine capstones on a future retaining wall.  Proving that I’m getting too strong for my own good: broke one of my Irwin Quick Clamps… which takes some doing!  Another delicious, delightful dinner at Marty & Merry’s.

6 August 2012

Called Goodro Lumber at 7:30 and was told that their truck was being loaded, soon to be headed my way.  So called Marty and took a rain check on our oft-postponed first-since-the-crash bike ride.  The Goodro truck showed up at 9, long after we would have returned from bicycling.  You know what would have happened had I headed out with Marty at 8…  As soon as the Goodro truck departed, called McDonough’s in Brandon about getting the Ranger tire repaired.  Was told to be there at 9:45, so put 40 psi of air in the right rear flat tire and drove as fast as I dared into Brandon, arriving at the service station 15 minutes later with 20 psi left in the tire.  Whew!!!!  Unfortunately, as soon as Mike McDonough saw the gash in the tire’s inside sidewall he said, “Unrepairable!”.  But then he told me about Brandon Auto Salvage on Route 7 in Leicester, a place I’ve driven past a zillion times and never paid any attention.  They have scads of “used but good” tires taken off wrecked cars and trucks.  Sure enough, a very nice used (but in better shape than the other three tires on the truck) 235 75R15 tire was just begging to be put on the Ranger, which was soon done… for a grand total of $65 (tire, mounting, spin balancing, and old tire disposal all included).  Now that’s a good deal!!!!  After getting water at Lynne & Perry’s, was back to Fern Lake by 11:30.  With time in hand before lunch, built a small ramp for the generator to sit level on as I move it incrementally down the wooden walkway.  After lunch, sawed a 25° angle the length of a 4x6 post, then dug the holes and planted that post plus two 4x4 posts that, together, form this slight turn in the walkway.  Then discovered that I will need 4½″ lag screws (vice the hundreds of 6″ lag screws that I have) to attach stringers to those particular posts.  So dug the holes for the next two in-ground posts, one of which will have to be wedged into a wide crack in an enormous rock, then called it a day. And in other good news: by throwing my laptop violently to the ground last night, a months-long problem with the computer’s video display has been fixed.  Somebody please explain that one to me… DISASTER!!!! When next I went to use my computer there was a zzzzzt sound, the smell of frying electronics, the finally-working-right-video display went black, and the computer became completely nonfunctional.  Was is just the video display that fried or was it the motherboard?  News in a week… The wise turtle would have been backing up all his files on a regular basis just in case his computer got sick. The smart turtle would have backed up all his irreplaceable data when the computer did get sick. Guess who’s neither smart nor wise????  Guess who’s sweating bullets right now????

5 August 2012

 

With all modesty aside, I do make an excellent, and oft requested, breakfast omelet.  Except for this morning when Alex asked for some of the leftover BBG chicken in his creation and I foolishly tried to heat it up a bit in my only frying pan.  The BBQ sauce promptly stuck to the pan which meant that the “omelets” stuck semi-permanently to the BBQ sauce and, consequently, became a hodgepodge of ingredients with some bits of egg mixed in.  We all cleaned our plates, so, though unsightly, the concoctions were still tasty enough.  The stump / brush fire was still smoldering when we finally ventured forth.  So Alex returned to fire tending while Katy and I went blackberry picking… which was the first time in her life that Katy has ever been berry picking.  Apparently that’s not one of the available options when you grow up in Houston, Texas.  We got a couple of quarts, and many scratches, in not much time, and didn’t even begin to deplete the stock in our patch out by Route 53.  Then Katy and I went canoeing while Alex encouraged the last remaining stump (the one the Ranger had had such a hard time towing into position) to become charcoal.  Katy & Alex headed back to Boston at 2… in the midst of an hour –long rainstorm.  I spent the afternoon making lasagna, swimming, and generally relaxing.  While over at Kate & Dan’s catching up on the blog postings another rainstorm started to arrive, so took shelter in their woodshed while trying to get the last little bit done and the email sent out.  Slipped and my laptop computer went flying.  Still works, obviously, but the cover no longer closes properly ‘cause one of the hinges is somewhat beyond broken.

4 August 2012


 

Let the record show that Katy did say, at least five minutes before calamity struck, “Doug, I think this is a bad idea!”  But that’s getting ahead of the story.  Katy and Alex arrived just before midnight, as expected, except that I had fallen asleep on the dinette settee that makes into a bed, and failed to hear them arrive.  Consequently, we somewhat surprised each other as they came though the main cabin door.  After dragging them out to see the walkway all lit up, we retired.  Early this morning Alex and I arose and Katy was induced to crawl out of bed.  After a quick breakfast, Alex got to indulge his pyromaniac fantasies while Katy and I used the Ranger to drag load after load of brush from the woods over to the bonfire site.  Having removed all the readily accessible brush piles by 11 o’clock, I figured I could snake the Ranger down the hill a bit further to retrieve a collection of limbs that were a long trudge from the lower “driveway”.  That’s when Katy let me know her opinion of the idea, forthrightly and directly.  Being overconfident and stupid, I ignored her advice until she yelled, “You’re on a rock!”, and the Ranger stopped moving.  “On” a rock was hardly an apt description.  I had backed up over an 850 pound (by later measurement) Leicester nugget and the truck suspension (and later the driveshaft) were firmly joined to granite.  That truck weren’t going nowhere without some serious machinations… which took the next four hours and every word in my sailor’s vocabulary (uttered silently, of course, in deference to a young lady’s sensibilities).  Have you ever had a truck fall off a jack while you were underneath it?  Katy yelled in the nick of time and then learned that, although her father-in-law is 62 years old, he can move with alacrity then properly motivated.  Wouldn’t have been so bad if the truck had toppled sidewise just once, but it happened four times as we raised the rear end, laboriously, using two jacks and makeshift cribbing, into the air so that the critical underside components were high enough to drag the rock out from underneath the truck.  In the process “we” (I seem to have gotten a mouse in my pocket while crawling around in the dirt) managed to poke a hole in the right rear tire.  Once again, Chris Thiel’s air compressor saved the bacon, as we could inflate the tire (very temporarily) when it came time to finally drive the Ranger away from the disaster site.  Then it was time to prepare ourselves (lake cool-down followed by cleansing shower), campfire, and food (BBQ chicken, homemade baked beans infused with campfire cooked hot dogs, Kingsley’s corn, garden salad, brownies right out of the oven topped with Ben & Jerry’s Vanilla Heath Bar Crunch) for the arrival of Marty & Merry (bearing gifts (plural) of wine that somehow all disappeared before a most delightful evening was adjourned.  After dark, Katy (lookout), Alex and I took Hopea Kanootti for a spin around the lake.  When we returned dockside, Katy and Alex most generously tackled the voluminous dinner dishes while I enjoyed, yet again, the calming waters of Fern Lake.

3 August 2012

Awoke this morning thinking of joints.  No, not that kind of joint!  I’m talking about the connection between two pieces of wood, specifically the longitudinals for the wooden walkway.  Decided that, for maximum strength, I need to have the lap joints fall either on (ideally) or close to the stringers that support the longitudinals, which are spaced eight feet apart.  So called Goodro’s first thing they opened and offered to trade them sixteen 2x4x12’s for twelve 2x4x16’s (works out to the same number of board feet of lumber).  Delivery expected Monday.  Have I ever mentioned that Perry is not only a fabulous chef, but also a brilliant carpenter?  He suggested coating the lag bolt threads with bar soap (he uses Ivory, but all I have is Dial).  Drove beaucoup lag bolts today and broke only the one I didn’t soap!  Installed the next pair of in-ground posts (one of which had to go exactly where a LARGE rock used to reside, until Tammy moved it out of the way with her backhoe), two sets of stringers, and their associated railing posts.  Surveyed (alignment only; elevations to follow) the next two sections of the walkway path, as the walkway needs to veer west 25 degrees in another four feet or people will knock their heads on a very nice, but very hard, cherry tree that is leaning just a tad too much downhill.  Can’t have that…  Then, once past the cherry tree, the walkway needs to make a precise 90 degree left turn, passing just so between a large oak and a small beech.  Trimmed the driveway vegetation just before diving in the lake.  I’m sure Alex and Katy will be mightily impressed with the manicured weeds when they arrive at midnight.

2 August 2012


Pooeee!  I don’t know what Delores has been eating lately, but she sure has gotten kinda gassy… if you know what I mean.  So off to Kampersville we went so she could have a therapeutic constitutional.  Back at Fern Lake by 8:30, whereupon I spent the balance of the morning shampooing the RV carpets.  Swear I removed a whole garbage bag of dog hair!  I also noticed that the big spaghetti sauce stain by the dining settee, dating from September 2009, is finally gone.  Heard some strange sounds coming from the down at the lake.  Investigated and discovered the Lake Dunmore / Fern Lake Association dive team busy removing Eurasian milfoil from around our dock.  Big smiley face!!!!  Preparing to run errands at noon, went up to the end of the driveway to remove the sign bracket from the post.  Did so, but then decided to get my tape measure to check the hole spacing on the sign post.  Wasn’t gone (to the RV and back) for more than five minutes, but in that time some ethically-challenged individual(s) absconded with my Werner 6′ stepladder.  #@!%$#@!!!!!  (BIG frowning face!!!!) Though hardly fit to drive (everything seemed to be colored red), went about my business.  A short while later was backing into Lynne & Perry’s single-lane driveway when I met Perry, at the blind corner, exiting said driveway in his truck.  It’s a good thing we both have good reflexes, as it would have been hard to explain to USAA how I was rear-ended by my brother-in-law while driving backwards.  On to Nop’s Metal Works to order ¼″ steel plate for the new driveway sign, plus some 3″ channel steel for modifications I need to make to the RV generator compartment in order to fit the new generator into said compartment.  Then to Martin’s to get a 7/32″ drill bit to ease the lag bolt breakage problem.  Returned to Fern Lake and drilled a hole which, like magic, accepted a lag bolt just fine.  Began drilling a second hole, got in a couple of inches, and the bit broke clean in two.  Double #@!%$#@!!!!!  So, to vent my anger and frustration, dug the holes for and put in the next two in-ground posts, then back to Martin’s I went, where I exchanged my “stubby” for a new (and hopefully more robust) 7/32″ bit.  After that gymkhana, I REALLY needed three fingers of Scotch a swim.  Apparently while I was so engaged, a State Police trooper stopped by to take get a full report concerning the stepladder heist.  The New Haven Barracks dispatcher says the trooper will call me later. Suspect that purloined stepladders are not high on the investigations priority list…

1 August 2012

 
NOAA Weather Radio said today was supposed to be partly-sunny deteriorating into thunderstorms and rain in the afternoon / evening.  Woke up to total overcast and five minutes of a rain shower at 5 minutes to 8… just in time to cancel Marty and my inaugural post-crash bike ride.  So worked in the shed all morning fabricating an 8½′ long by 3′ wide ramp (made entirely out of wood otherwise destined for the burn pile) to transition from the lower “driveway” surface up onto the wooden walkway… whose deck is some 15″ above the current ground level.  The ramp just sits (very securely) on the end of the walkway, so it can easily (if you’re very strong… or have a helper) be moved out of the way when vehicles need to get through that area.  Needless to say, getting the ramp single-handedly from the fabrication site to the installation site was a bit of a challenge, especially negotiating the 120° turn at the first landing.  By the time that was accomplished the skies were, indeed, partly-sunny.  So set to work digging holes for the next set of in-ground posts.  Got the posts in fine, but, when I broke the fifth ¼″ lag bolt trying to attach the stringers, I called it a day.  The problem is either: (a) I’ve gotten too strong for my own good, (b) the 3/16 drill bit I’m using for the pilot holes is just a tad too small, (c) the 20+ year old 4x4 posts I’m reusing from the old stairway are just too dry and tough, (d) they’re using really inferior steel to make lag bolts these days, or (e) all of the above.  Ate a whole can of spinach (3½ servings if you can believe the label) with dinner tonight.  Those lag bolts won’t have a prayer tomorrow…