31 August 2011

Perry and I finished installing the soffits, then put two coats of latex enamel satin finish paint on the fascias, feature strips, and the soffits.  The first two could be done standing up; the soffits had to be done lying down, scooting along on your back after every two feet was painted, which sounds a lot easier than it was. Tammy Walsh came over to give me her invoice for guiding the car turnaround area retaining wall construction.  First bill I’ve gotten in months that was less than I had estimated.  Unfortunately, the difference between estimate and actual isn’t going to keep me out of debtor’s prison, but it was a nice surprise anyway.  After the painting was done, Perry and I applied 30# felt to the entire roof area, effectively waterproofing it (and the building beneath) forevermore.

30 August 2011

In the morning Perry and I installed the feature strips (narrow boards nailed to the fascia to introduce an additional shadow line… a subtle but important Architectural Digest detail) and the soffit vents (3″ x 8 foot louvered metal strips that let air into the building just below the roof line).  Then we began cutting and putting up the soffits.  These are being made from ″ PTS underlayment instead of AC plywood… far less costly and nearly the same quality.  Unfortunately for our elderly bodies, the scaffolding is about three feet too tall for working on the soffits and it would not be worth the substantial effort to lower the working level to the right height.  Therefore most of the soffit work has to be done sitting cross-legged with both hands holding lumber and/or tools over your head.  Great exercise… for about five minutes.  After that it’s just plain tiring.  As Perry says, “Think of all the fitness club dues you’re saving by doing this kind of work!”  By the end of the day about 75% of the soffits were nailed into place… and I was almost too tired to drink my after-work beer.  Notice I said “almost”.

29 August 2011




The only local “damage” from the hurricane was one fairly large oak branch that came down into the recently created shed turnaround area extension… where I was going to park the Ranger for the storm but didn’t due to tiredness. Obviously, if I’d done as planned, the Ranger would have suffered grave bodily damage.  Delores and the shed came through just fine, with only the upper floor of the shed getting wet from water bouncing off the scaffolding and into the door openings.  Elsewhere in Vermont there was much more severe damage, mostly from flooding.  U.S. 7 (the main north/south highway on the west side of the state) is cut in Brandon and again south of Rutland; state routes 125, 73, and 103 (routes across the mountains from the east and southeast) likewise are closed; Otter Creek in Rutland was 8 feet above flood stage and still rising as of this morning. Perry finished installing the roof sheathing before lunch.  Marty came up to take the commemorative picture for this major construction milestone.  In between occasional moments helping Perry, I spent most of the day priming all of the fascia, feature strip, and soffit lumber… turning my hands completely white in the process.  In the afternoon Perry cut, then we installed, all of the fascia boards.

28 August 2011

Here’s a gender testing question for you: Does being low (not out, just low) on beer and honey roasted peanuts constitute an emergency sufficiently dire to go out into the teeth of a hurricane for resupply?  Not that “Hurricane” Irene was worthy of her moniker – highest wind gusts were only 33 mph, though we did get 7 inches of rain… that immediately soaked into the gravel here at Fern Lake.  After the run to Hannaford’s, spent the day reading, beating my brain into mush trying to solve a couple of Master Class sudokus, and trying to figure out how to stay out of debtor’s prison while still finishing the woodshed construction project this year.  In a month or so you should be able to write to me care of cell 5733.

27 August 2011

First thing in the morning I clambered atop Delores and liberally applied silicone sealant to several cracks in the bathroom skylight and over the forward cabin.  Hopefully that will keep the 4 – 7 inches of rain that we’re supposed to get tomorrow outside where it belongs. Perry and I had a productive day, getting about ¾ of the ″ Advantech tongue & groove roof sheathing cut, put up, and nailed down.  Concentrated on the north, east, and west sides of the roof, as that is the direction from which the high winds associated with Hurricane Irene are expected. Perry thought we could have gotten the whole roof sheathed if I hadn’t insisted we stop that work in order to secure the worksite for heavy seas.  After Perry left to attend to his own house, I moved all the patio furniture and associated paraphernalia on Kate & Dan’s outdoor porch into their indoor porch.  Then I moved the campsite lawn furniture into the shed garage and made some attempt to secure all the stacks of wood scattered about the joint. Frankly, I was running out of steam by the time I got to that task... so if it all blows away I won’t be horribly surprised.  Another 8:30 “dinner” straight out of the can… and too tired to even open a beer.

26 August 2011

Took a plate of homemade lasagna (Chree’s recipe, so should be much better than my recent “creations”) down to Marty & Merry so they wouldn’t have an excuse to skip lunch.  Perry stopped at Goodro’s on the way over this morning to pick up the materials needed for the shed fascias and soffits.  Another $450 added to my burgeoning tab!  Does anyone know where I can sell two kids into slavery to raise some cash?  While awaiting Perry’s arrival, figured out (again) that I am a total idiot.  I already knew that the light switches for the lower level of the shed are in the wrong location, but that happened because a large, immovable-by-hand-and-I-don’t-have-a-backhoe rock forced me to alter the auxiliary storage area design after I was committed to having the switches installed where they are.  However, I told the electricians that the light switch and electric outlet on the second level would be on the right side of the person-door (facing outwards), so they ran the PVC conduit to accommodate that placement.  I then special-ordered a left-hand door, i.e., a door with the hinges on the left side as you face the door from the outside. So, as configured, the light switch for the upper level would be behind the opened door.  Wrong answer, you idiot!!!!  Spent most of the day (when not actively engaged with Perry) trying to figure out how to have my cake and eat my foot at the same time. Jeffrey Many stopped by to retrieve two tools he inadvertently left behind the other day.  Perry and I put up the ledger boards for the soffits, which are horizontal 2 x 4’s nailed to the shed sheathing, the bottom edges of which are exactly level with the bottom tip of the roof rafters.  Then we installed the lookouts, which are short pieces of 2 x 4 that run perpendicularly from the ledger board to the sub-fascia 2 x 6’s (installed yesterday) that cover the rafter ends.  The soffits will be nailed to the ledger board, lookouts, and sub-fascia.  Sent a large plate of lasagna home with Perry, partial thanks for the constant stream of wonderful vegetables that he has been bringing me from his garden.  Had some lasagna for dinner myself… weren’t too awful bad, neither!

25 August 2011

A totally dreary day with on-again, off-again showers.  Perry and I worked steadily, up on the scaffolding when the rain abated putting on the sub-fascia (horizontal 2 x 6’s that are nailed to the ends of the roof rafters, onto which the fascia boards will be nailed), inside the almost totally dry shed setting up for the collar tie installation and putting in the rest of the hurricane ties when showers were upon us.  Yes, you read that last sentence correctly… except for one minor pinhole leak that will be fixed with some duct tape tomorrow, the upper and lower levels of the shed are (finally!!!!) protected from water intrusion.  At the end of the day the sub-fascia was attached to the rafter ends all the way around the building and that roof ain’t never coming off them walls, I don’t care how hard the wind blows.

24 August 2011



Another 8:30 “dinner” eaten straight out of the can... with a beer chaser.  A very long but very productive day. Perry and Jeffrey Many arrived simultaneously just on 8 in the morning.  While Perry continued cutting jack rafters, I got Jeff started on installing the shed garage door.  Jeff needed one additional framing member put in and one tweaked into better alignment with the door trim; both jobs quickly accomplished. Back working with Perry, he informed me that he had awoken at 2:30 am and realized that the northeast hip rafter was not cut right. While he chewed up some more 16 penny nails, my mission was to unfasten that rafter from the building without destroying anything.  Took some doing (when Perry and I install something, it’s meant to stay put for 400 years), but we got ‘er out and in reasonably intact condition.  Once that hip rafter was cut correctly and reinstalled, we set to work on installing the rest of the jack rafters. During periods when Perry was cutting jacks (and not to be disturbed short of nuclear holocaust), I started installing hurricane ties on the exterior side of each rafter.  Originally I was going to install only one tie per rafter on the interior side, but the shade of Mike Holmes (of the HGTV program Holmes on Homes) nagged me into doing the job right the first time (at an additional cost of $43 in materials, a trip to Goodro’s, a couple of hours of my time, and some blisters on my too dainty right hand). Doing the job right meant installing two ties on each rafter diagonally from each other, one inside and one outside.  Jeff finished the garage door installation mid-afternoon, getting a 10″ radius single track system to work (at my urging) vice the low-headroom, double track system that he had wanted to install.  The single track installation detracts much less from the shed lower level ambiance. However, Wayne-Dalton (the door manufacturer) had sent the wrong insert for the windows and the wrong remote control… so I’ll be seeing Jeff again soon. While I was making the aforementioned trip to Goodro’s for more hurricane ties, Perry made the plumb cuts on each rafter end.  When I returned, he expressed unhappiness with the quality of that work, so we re-snapped the cut lines and he took another whack.  Pikey Many (whose father, Mike, is Jeffrey’s cousin) stopped by with his written proposal for installing a standing seam metal roof on the shed.  Pikey’s proposal was within $75 of the one I got from Tim Clarke, so I awarded Pikey the job on the spot, with expected completion no later than the first week in October.  With evening upon us, Perry and I decided to call it a day… and then spent an additional hour securing the site for the thunderstorms predicted for tomorrow and the remnants of Hurricane Irene that will be here this weekend.  With six sheets of roof sheathing temporarily attached to the rafters and covered with two of my least worthless tarps, we hope the building will stay drier than during previous deluges.  Eternal optimists, that would be us.

23 August 2011



Had to turn on Delores’ furnace to take the chill off during breakfast. Furnace worked fine… a nice surprise. The plan for this morning was to get the four hip rafters cut and installed.  Those are the rafters that run from the main rafter to the four corners of the building.  The hip rafters have very complicated compound miter cuts that have to be done perfectly for the roof to look right in the end.  Suffice it to say that at about 11 o’clock I had to make a quick run to Goodro’s for three more 2 x 8 x 14’s while Perry chewed and swallowed an entire bag of 16 penny nails.  While at Goodrow’s I also picked up the people door for the shed that had been special ordered last week.  Marty, his son Ricky, Ricky’s wife Caroline, and their twin babies Juni and Kolya, came by mid-afternoon to learn some new vocabulary view the goings-on.  By the end of the day all of the common rafters, the four hip rafters, and four of the forty jack rafters had been cut (correctly) and installed, along with about half the hurricane ties that keep the roof attached to the rest of the building in high winds.

22 August 2011

Spent a good part of the morning taking down, then removing the root ball, for a really nice 8″ maple that was growing near the northeast corner of the shed… a tree that I really wanted to keep.  Perry finally convinced me that ½″ clearance between the roof overhang and the tree really wasn’t enough, especially during a nor’easter.  Used the five-fold block and tackle that Zook donated to the cause to pull the tree over, roots and all, after I first ruined my just-sharpened Jonsered chain by using it to cut a few more Leicester nuggets that were lurking, sight unseen, next to the main taproot that I was really trying to sever.  Perry spent the morning double- and triple- checking the roof rafter layout measurements.  Just before lunch we erected a second level onto the north end scaffolding, which put our heads about 16 feet above the ground… perfect for working on the roof and associated rafters. We then put up scaffolding wall brackets (borrowed from Bob Hillman, Perry’s has-everything neighbor) at that same height along the east wall.  Looking at our accomplishment, Perry said, “You know, Bob has a bunch more of those wall brackets, and if we put them up on the south and west walls, we’d end up with a super-highway all the way around the shed at just the right height.”  So, during a lunch eaten in his truck, we went on another raid to Bob’s construction supply depot and took away the scaffolding materials needed for said highway.  By mid-afternoon we could walk all the way around the shed at roof rafter height.  Perry then started cutting the ridge rafter and the king common rafters, then showed me how two people can easily erect a ridge rafter in the right location and without benefit of a sky crane.  Pretty slick!  Unfortunately, when we went to install the two king common end rafters, they seemed to be ″ too short.  Perry double checked his calculations… but they were correct.  Then he measured the distance between the north and south end walls.  Perhaps we shouldn’t have been surprised that they were ″ further apart after hanging the wall brackets on the south wall and then walking around on the scaffolding for awhile.  Our conundrum at that point was that we had used the only four wall jacks the Bob Hillman owns to straighten the east and west walls… and didn’t want to move those jacks for fear that those two long walls would then warp.  I suggested we use my logging chain and ½ ton come-along to pull the two end walls back together.  Worked like a charm!  Like magic, all of the king common rafters then fit together with the ridge rafter just like they were supposed to.  Just as we were congratulating ourselves, the sky turned suddenly black (completely unforecast!), and we just had time to get (almost) everything under cover before the deluge hit.  Then I remembered that the camera was still on the tripod up in the tree stand.  Running pell-mell down through the woods, I scrambled up the ladder… only to discover that the hemlock’s branches were affording the camera perfect protection from the storm.

21 August 2011

Perry came over first thing to move the east and west wall braces so that I could put one of my worthless tarps over the shed floor to at least slow down the waterfall into the lower level from the forecast thunderstorms this afternoon.  Perry then drove me back to his house so that Lynne and I could drive into Burlington together… she to do some shopping with Alverta and me to retrieve Delores.  A delicious early lunch with Alverta, then she and Lynne took me over to Pete’s RV (located a mile from Alverta’s condo).  Delores was there, looking completely out of place among her 2011 cousins.  The driver’s window was down and the door unlocked (great security!), the keys were hidden where I was told they would be (better security), but the safety latch on the main cabin door was thrown, so we couldn’t get in that way (wonderful security).  Uneventful trip back to Middlebury (cruise control, taillights, and steps working fine; new refrigerator humming away in back).  Spent my last C-note at Hannaford’s, then discovered that the shelf and bin layout in the new refer is much less user-friendly than in the old model.  Ended up just throwing everything in willy-nilly… which those of you who know me well know drove me more than slightly nuts.  In the midst of moving all of my “stuff” out of Kate & Dan’s house and back into Delores, the power went out… while the sheets from the bed I had been using were still in the dryer.  Pushed ahead with decamping and cleaning up.  Got that done and still no power, so moved Delores back over to her usual resting spot on our property.  Lo and behold, power was available at our electrical panel when I went to hook her back up.  That’s strange, I thought, for Delores to have power when Kate & Dan don’t, ‘cause our feeds come off the same pole and transformer.  Back over to the house I trudged, to discover that Kate & Dan also had power… and their security system was doing all sorts of strange and unusual things about which I had no idea.  The phone rang, but, it not being my house, I ignored it.  While I was upstairs remaking the bed, the front door opened and a man called, “Hello. Brandon Rescue.”  Apparently, when the power came back on the security system called 911, whose operator called the house to ascertain whether or not there was an emergency, but receiving no answer had to assume there was, so dispatched the Brandon emergency response person (EMT), the State police, and an ambulance.  A quick phone call from the EMT cancelled the police and ambulance response.

20 August 2011

 
Got up a little early, so went for a leisurely ½ hour swim, which definitely is the way to start the day.  There was just a hint of fog rising off the flat calm water.  Absolute Heaven!!!!  On his way over here Perry went on a raiding mission at his neighbor’s place (Bob Hillman – who also is a building contractor and has every tool or device known to man).  Perry came away with a pickup full of scaffolding.  So after we verified that the west wall was within 1/64″ of straight, we erected the scaffolding to allow access to the upper level of the north wall.  In less than an hour we had a super-highway up there, which made sheathing that wall a breeze, will enable us to access the roof rafters on that end, and will make putting on the cedar shingle siding much easier.  We put one end of my aluminum scaffold on the north end scaffolding and the other end on my Little Giant folding ladder and, voilá, we could sheath the east wall.  When we got to the south wall Perry informed me that I hadn’t ordered enough ½″ CDX plywood to complete the building sheathing. Ooops! It was now about 2:30 in the afternoon on a Saturday, when virtually every lumber yard is closed, closed, closed.  Fortunately, Martin’s was still open and had in stock the additional four sheets we needed… albeit somewhat more expensive and definitely lower quality than what I get from Goodro’s.  Desperate times call for disparate measures!  By quitting time, which used to be 5 o’clock until I started working with the slave driver, the shed upper level walls were completely covered with plywood… and we were two tuckered puppies.  After the work site was secured for rain and an cold, refreshing libation drunk, dinner again was served right out of the Tupperware at 8 o’clock.

19 August 2011

 

Since we’ve been working until 7:00 pm every night this week I have been resolving the tension between after work swimming and eating in favor of the later.  So this morning I got up and dove in.  Of course, Perry called while I was underway, so we played cell phone tag for awhile.  He arrived, via Taylor Rental and Goodro Lumber, with a surveyor’s transit and a bag of fresh vegetables.  I’ll leave it to you to figure out which came from his garden.  Using the transit we quickly determined that the top corners of the shed walls were out of level by 5/16″.  Considering all the drama that accompanied pouring the foundation footers and the concrete columns, then sawing and placing the beams, etc., I don’t think that was too shabby.  However, than much error had to be corrected by shimming the double top plate, which we spent the rest of the day accomplishing to within 1/64″.  And you thought I was a perfectionist!!!!  Brian arrived from Goodro Lumber just after lunch with ANOTHER $1,000 worth of lumber, which should be most of what is needed for the shed roof.  Then Pete’s RV called to let me know that Delores continues to act perfectly while in their care, so they weren’t able to fix either the cruise control or the steps.  They basically accomplished three of the six items on the list (refrigerator, taillight, VT annual inspection)… and will give me back the keys in exchange for $2,100.  Not only will the kids not be getting an inheritance, pretty soon I’ve have to start borrowing money from them.  On a positive note, the grass that Katy and Chree planted on the shed east side has sprouted everywhere but where we are constantly walking.

18 August 2011

Chree and the dogs left for Virginia via Connecticut soon after Perry arrived.  He and I set to work building the west wall, which, because it has 13 feet of doors in a 20 feet span, had to have an enormous header made from two 2 x 10 x 20’s sistered together with pieces of ½″ plywood to make a beam 19′ 6″ long, 9¼″ high, and 3½″ thick… which weighed in at 125 pounds.  Omph!  Once we got the wall built, the two of us were able to raise one side 3 feet off the ground onto my sawhorses… but that’s all we could do.  Marty!!!! While we were waiting for a rescue party from the north to arrive, we went off to Perry’s friend Don Ross’ place on Lake Dunmore to liberate four sections of scaffolding.  Returned to Fern Lake, with Marty’s he-man help and some grunting, we hoisted the west wall to a vertical position.  Meanwhile, Tim Clark stopped by with his written estimate for installing a standing seam metal roof on the shed.  His price went up $500 from his earlier verbal estimate… and is nearly $1,000 more than my budget. Hmmm!!!!  On a positive note, Mike Many (who lives a half mile north on Lake Dunmore Road ) and his son, Pikey, stopped by to look at the roofing job.  Unfortunately, their verbal estimate was in the same ball park as Tim Clark, but we’ll see (next week) what their written estimate comes in at.  After Mike and Pikey left, Perry and I cobbled together the framing for the north and south walls, raised those walls into position, and plumbed perfectly vertical all four walls of the shed.  Figuring we’d done enough damage for one day, we put away tools and cleaned up the job site (thunderstorms in the forecast for tonight), then repaired to the comfort of Kate & Dan’s porch for a couple of cold ones and to figure out what lumber to order for building the roof.

17 August 2011


The Goodro Lumber truck arrived at 8:30… with the wrong type of wood!  I definitely had ordered their Western Grade lumber, which is somewhat more expensive but definitely much higher quality, than their Eastern Grade stock.  The salesperson wrote down the right type, but somehow all Eastern Grade got loaded on the truck and put on the invoice.  So I told the driver to go away and get the right stuff.  Perry arrived just before 9 while the Goodro driver and I were sorting things out and confirmed my decision.  To their credit, not only was the truck back with the right lumber by 10:30, but the salesperson called to apologize for the mistake.  Perry and I made sure the chalk lines for the shed walls were in the right place and formed a PERFECT rectangle. (Nice working with a pro!)  Then Perry set to work laying out the stud placement on the wall sole plates.  That critical task was fairly tricky because the studs have to line up with the roof rafters (in order to properly carry the roof load down to the shed foundation), a hipped roof is quite complicated with respect to the rafter placement, and there will be three large doors in the west wall.  While that was going on, I sorted though the large pile of previously used but maybe still good 2 x 4 x 8’s, pulling out lumber that could be made into wall studs, then sawed them to be precisely 92⅝″ long.  A bottle of my finest wine to anyone who can tell us why wall studs are 92⅝″ long, and not 93″, which is what I think they should be.  Once the layout was done, assembling that actual east wall framing took relatively little time. The wall was built flat on the shed deck, which is a whole heck of a lot easier that trying to build it upright.  We checked that the wall was PERFECTLY rectangular, then installed the top portion of the sheathing and 30# felt.  Just as we were finishing, Marty and Merry returned home from their lawful endeavors, so I hollered down the hill for some strongman assistance in raising the wall to a vertical position.  Perry and I might have been able to do the job ourselves, but with Marty’s additional assistance, the wall rose upright almost of its own accord.  Perry installed braces while Marty and I hung on for our lives, as having the wall fall down, in either direction, would not have been good for morale.  After incidental tweaking and putting away of tools, Perry and I were ready for liquid refreshment by 6 o’clock.  Chree came over to admire our day’s accomplishments, and congratulated Perry on having survived a day working with me.  After dinner I returned to the scene of the crime and created the additional 26 wall studs that we will need for tomorrow’s fun in the sun.
P.S.  Based on many phone calls to/from Ed at Pete’s RV throughout the day, Delores is going to get a new refrigerator (to the tune of $1,700!!!!), they can’t fix the main cabin door steps if they’re working perfectly, the generator is totally messed up (told them to leave it as is), and, when last heard, they were trying to figure out just what is wrong with the cruise control.  Ed did agree to take my first born male child in return for the new refrigerator, but only if I threw in my left leg as well.

16 August 2011

Rain, rain, go away, we’ve got things to do outside today!!!!  Hmmm, Mother Nature doesn’t seem to listen to me either…  Then again, sometimes I don’t even listen to myself too well, though I’m getting better at not talking out loud while working alone.  Chree and I spent some quality time in the morning at Goodro Lumber, ordering an exterior people door for the shed plus $$$ worth of framing lumber and sheathing.  As forecast, promptly at noon the rain stopped, and the sun came out to stay by 1 o’clock.  So we dragged the totally useless big blue tarp (maybe I wasn’t so dumb after all) off the top of the shed, then set about installing the east wall rim joist and then inserting lag bolts in the north wall rim joist so as to permanently sister it to the beam on that end of the shed.  For a married couple, things went very smoothly.  We were done easily by 4:30.  Took the first of what will be a series of photos of the shed upper level construction from the vantage point of the tree stand.  Perry came over at 6:30 to lay out lines for the shed upper level walls… and check out the quality of our beer supply.

15 August 2011

Chree and I left at the crack of dawn to take Delores to the RV doctor.  The main cabin door steps, of course, continued to work perfectly.  On the other hand, the cruise control was inoperative (worked fine last time I took the RV into Middlebury) and when we got to Pete’s RV in South Burlington, Chree said, “Did you know that your right taillight isn’t working at all… no brake light, no tail light, no turn signal?”  One more thing to add to the list. We were back at Fern Lake by shortly after 10.  Since it was raining, and forecast to continue doing so interminably, we decided to spend the day inside the comfort of Kate & Dan’s house, Chree writing Welcome to Kindergarten letters and I reviewing the shed upper level designs and associated engineering load calculations.  And the first “tool” I needed was the pencil sharpener that is sitting in plain view on the RV driver’s console.  Told you!!!!  Perry came over after dinner for a couple of hours planning the shed upper level building campaign.

14 August 2011

Doug’s Wonderful Omelets for breakfast (and you always thought DWO stood for Deck Watch Officer).  Then Alex and I tacked the job of installing the 2 x 10 rim joist for the west wall of the shed, followed by properly securing (with ″ x 4″ lag bolts) the previously installed (with deck screws) south wall rim joist.  Alverta arrived mid-morning after a scenic tour of Vermont en route Fern Lake.  Lynne and Jake (her son, whose only previous visit, alas, went unrecorded) came over for a brief look-see around noon.  Chree, meanwhile, spent some time putting painter’s putty into the countersink holes for the finishing nails used to attach the trim to the garage door framework.  We put Delores’ big blue tarp, folded into quarters, over the shed deck.  Should have done that in April.  (Dawn comes late over Marblehead!)  Late lunch / early dinner was Chree’s Delicious Lasagna (and you always thought CDL stood for Commercial Drivers License).  After Alverta and Katy & Alex headed out, I removed from the RV all but the one tool I will absolutely need this week, storing the collection in the Ranger.  Then I drove the RV over to Kate & Dan’s, where it immediately started to rain as we unloaded all of our worldly goods (except for the things we will need most), including the entire contents of the refrigerator / freezer, into their house… which they have MOST GENEROUSLY allowed us to use while Delores is at the doctor.  The dogs, of course, were most intrigued by the smells left behind by Kate & Dan’s dogs and cats.

13 August 2011

Chree and I installed the ½″ plywood sheathing over the garage door framing, part of which had to be fastened to the concrete columns with copious quantities of Locktite PL375 and nails fired from the Remington.  Needless to say, Chree and the dogs vacated the county while the Remington was in use.  We were just installing the last piece of plywood when Alex & Katy arrived from Boston.  After lunch, Alex and I installed the 30# builder’s felt (aka: heavy weight tar paper) and PVC trim around the garage door opening while Chree and Katy raked stones off the slope on east side of the shed in a (vain????) attempt to prepare that plot for grass seeding.  Chree’s idea of what constituted a smooth and stone-free planting field and mine were considerably at odds, which caused a mutiny in the ranks.  I got both the raking and the trim installing done eventually, after which some cooling down time in the lake seemed like a good idea.  We planted the slope with a 50/50 mixture of Paris Farmers Union conservation mix and winter ryegrass.  Lynne and Perry joined us for dinner cooked over and eaten around the campfire.  Somehow Doug got nominated to do all the dishes after dinner…

12 August 2011

Chree and I began the task of framing the garage door opening in the north end of the shed lower level.  First task was to attach some 2 x 4 studs to the end concrete columns and the footers.  To do that I had Perry’s Remington gun that uses 22 caliber blanks to fire 2½″ nails through the lumber and into the concrete.  The first “shot” I took was a tad too close to the edge of the column, causing a fair-sized chunk of concrete to go flying off the corner, hitting Chree in two places and then bouncing off Shlomo.  Ooops!  After Chree and the dogs had taken refuge in the RV, the next ten shots went just fine… and those studs ain’t never coming off.  The king studs took some adjusting to get them to form a square opening, but after three or four tries they were correctly positioned.  Put the jack studs into position and all of a sudden the opening was a ¼″ too narrow. WTH,O!!!! After much head scratching, determined that the pressure treated lumber I was using was 1″ thick vice the 1½″ it was supposed to be.  Then found out that the project architect (his name is Doug) had miscalculated the header length by 1½″ too short, which probably is an accurate description of the architect himself.  Chree came up with the brilliant idea of inserting a 3½″ square piece of ¾″ plywood at each end of the header (held in position by a slathering of Liquid Nails and 3″ screws­), and presto chango, problem solved.  By the end of the afternoon the basic framing was in place, formed a rough opening of approximately the right size and shape, the header was level, and we were still married.  Can’t ask for much more than that!

11 August 2011

The dogs, of course, wanted their usual 5:45 outdoor excursion and breakfast.  They hadn’t been carousing until after midnight, unlike two tired humans.  All in all a fairly slow day.  Up to Lynne & Perry’s to do a couple of loads of laundry, then on to Middlebury for supplies at Goodro Lumber and Paris Farmers Union, with a stop at Taylor Rental to inquire about pneumatic siding guns (they don’t have).  Then spent a few hours raking smoother the shed construction site and removing tree root fragments and too large rocks.  Dan came over after dinner for a couple of relaxing hours chatting by the campfire… and roasting our share of marshmallows.

10 August 2011


Bob arrived at 8:00 with a load of bank run gravel.  By 9:30 he had brought in three more loads.  Tammy arrived about 8:30 and set to work sawing up and hauling away the evil Doug-whacking maple trees, with some limb removal help from me (tree limbs, not my limbs). Upon Bob’s final return we set to work placing cap stones all along the perimeter of the car turnaround area retaining wall. About 1 o’clock Bob went to get yet another load of gravel while Tammy and I took a breather and quick lunch break.  By 2:30 the retaining wall was complete and the turnaround area filled in and leveled off.  So then we set to work extending the shed turnaround area and associated retaining wall.  To get the woods out of the way, lumberjack Bob just bulldozed the trees aside, including an 8″ maple.  Dan came over to observe and help as this was going on.  An hour and a half later, the shed turnaround area had been extended 20′ east and Bob had built a third retaining wall all by himself and without ever leaving the excavator cab.  Amazing just doesn’t come close to describing the touch he has with that machine.  After a quick beer, swim, and shower, Dan and Perry came over for dinner at 5:30.  We left, in company with the Lapidus’, at 6:15 for Dorset, where Kate was appearing in the British comedy Noises Off.  To describe that play as hysterical would be a gross understatement.  To describe Kate as one very fine actress would also be a gross understatement.  After the final curtain we waited around and then spent some time chatting with the cast.  A totally FABULOUS experience.  We got back to Fern Lake at midnight.

9 August 2011



Bob LaPorte arrived a few minutes before 8:00 with the first of what would turn out to be four loads of bank run gravel needed to backfill around the shed cellar hole.  Tammy Walsh arrived somewhat later.  The three of us spent a very productive day laying rocks.  By quitting time the car turnaround area retaining wall was done except for a course of capstones.  All went quite smoothly until a few minutes before Chree and the dogs arrived.  We decided that three medium sized maple trees had to be removed in order to have the car turnaround area be the desired size.  Ace lumberjack Bob used his excavator to simply knock them over, roots and all.  Where they fell blocked Tammy’s Kubota from exiting the work site, so I took the Jonsered in hand and started bucking the trees into lengths.  When I cut the root ball off the end of the largest tree the root ball tipped back upright.  Unnoticed by me, that root ball was attached to the adjacent tree, which also promptly resumed an upright position… right where I was standing.  That upstanding tree smacked me pretty good on my already hurting right side, sending me tumbling to the ground.  Fortunately the Jonsered has a chain brake, which my fall activated… saving me from serious injury.  Unfortunately, as I fell somehow my right hand came in contact with the recently professionally sharpened so very, very sharp chain, which resulted in Chree finding a welcoming puddle of blood in the RV sink upon her arrival.

8 August 2011

 

Bob LaPorte arrived just after 7:00 with his Komatsu PC75R excavator. Tammy Walsh, with her Kubota B3200 loader / backhoe, arrived somewhat later, at nearly the same time as Alverta, who came down to watch the circus.  Bob’s first mission was to dig out the triple maple stump alongside the driveway.  He went about halfway to China before he could get that beast out of the ground.  Ask me later how we’re going to move it to a burn pile.  Bob then tackled the red oak stump that I had cut close to the ground so that the crane could get into position for hoisting the underground storage area roof.  That stump came out fairly easily.  While this was going on Tammy was using her machine to haul the downed trees off the house site so that the area is clear of us to dig up more stones and fill later this week.  She will be taking those trees for firewood.  Bob then started grading the area from the RV parking spot to the shed.  Right under where I had framed the underground roof there was a small rock, about a foot square, that I couldn’t get out with a shovel, so the top of that rock became the grade level for the underground roof frame.  Bob dug and dug, then dug some more, before hauling out of the ground a 4′ by 4½′ by 5′ monster, approximate weight 6¾ tons.  Bob’s excavator can only pick up about four tons, so we lassoed the monster with three logging chains (breaking two of them in the ensuing struggle) and he dragged the rock down the hill to become the first part of the car turnaround area retaining wall.  That rock had four good faces.  Do you think we could get any of them facing north or on top?  Right first time!  After a half hour of poking and prodding we said it is where it is and we’ll just have to deal with that later.  Where it was was 30″ from the shed foundation wall.  We tried four times before we got the rocks we put in that 30″ gap to not fall down when we put the next rock on top.  We had similar “fun” with many of the other rock placements.  By the end of the day I was pretty well whipped and we had the first course of rocks laid for about half the wall… and the supply of “good” rocks was dwindling rapidly. Had to take a swim to get enough dirt off so I could take a shower.  At various times during the day Dan, Marty, Merry, and Fran Viko stopped by to view our endeavors and lend their moral support.

7 August 2011

Took Delores up to Kampersville to dump the holding tanks… right in the middle of a bicycle and running race taking place the entire length of Lake Dunmore Road.  Going north I was against the flow; coming back south I drafted behind one of the cyclists… which meant we went really slow up the hills and almost got up to the speed limit going down.  The main cabin door steps worked perfectly and the propane gas gauge has finally inched below the half tank mark.  Obviously Delores is trying to convince me she doesn’t really need to go to the RV doctor.  Nice try but no cigar!  Upon return to Fern Lake filled both holding tanks with water and added the chemical that will (hopefully) clean the tank level indicating sensors.  Then set about making the building site ready for backfilling the shed cellar hole and building the house turnaround area retaining wall.  Moved crushed stone, building rocks, extension ladder, and radial arm saw (which required Dan’s musculature) to where they won’t be in the way.  Got everything done by 3:30, so went over to Dan’s to help him burn the slash from our chainsaw activities the other day.  After sweating over the hot fire for an hour and a half, the lake felt REALLY, REALLY good.

6 August 2011


While waiting for Jeff Many to arrive, shaped several rocks that need to fit around the electrical conduit. Jeff finally got here (an hour later than scheduled) and we put together a garage door order.  Much as it pained me to give business to a company owned by the Chinese, the Wayne-Dalton model 8300 was less expensive and of better quality than the doors offered by the competition.  Some consolation: at least the doors are manufactured here in the States.  After Jeff departed I beat feet to Goodro Lumber to pay my July man-toy bill… and get a bunch of goodies needed to frame in the garage door opening.  Didn’t write out a list so, of course, I forgot to get two items, including the expanding foam insulation needed to seal the top of the rock walls to the rim joist.  Dan came over shortly after I returned to Fern Lake and again volunteered his services.  With his help we finished all of the rock laying and cementing needed before the cellar hole can be backfilled.  By my reckoning there are only 36½ cubic feet of rock walls to be built in order to completely seal the woodshed lower level.

5 August 2011


The thermometer in the refrigerator registered 40 degrees this morning and frost again is starting to form on the cooling vanes!  So obviously Delores overheard my making her doctor’s appointment.  (Pssst, I’m not cancelling the appointment, but don’t tell you no poo.)  Another full day placing and cementing rocks on the underground roof ledge. Was making okay progress until my back reminded me that I’d forgotten to take the prescribed Ibuprophen dosage at noon.  Lesson learned: don’t put the rim joist on until the rocks underneath it are laid and cemented.  Trying to work under that joist (which is fastened to the south end beam with a full tube of PL400 adhesive and many screws, i.e., it ain’t coming off without using high explosives) is a royal pain in the neck.  Tammy Walsh and Fran Viko stopped by late afternoon so that Tammy could look over the work planned for next week… and know what equipment to bring on Monday.  Tammy made some flattering comments about my masonry work, which made my day.

4 August 2011

Worked all day to get the first course of stone dry-laid on the underground roof ledge.  The sad part of that exercise is that Steve Osmer had already selected a bunch of rocks and put them on the ledge, ready for my final positioning.  As you enter the garage / storage area, your eye is immediately drawn to the wooden triangle, square, and circle that are inset into the face of the ledge… and consequently, the first rocks you notice are those just above those symbols.  So positioning those rocks to achieve a creditable artistic presentation was fussy work… that took all day.  Made arrangements to take Delores to the RV doctor (Pete’s RV Sales and Service in South Burlington) week after next.  Dan and I were invited to dinner Chez Lapidus, with grilled salmon, Kingsley corn, and blueberry pie on the menu.  Another delightful evening with our wonderful neighbors!

3 August 2011

Spent the day over at Dan’s removing limbs (wooden, not human) and taking down trees to open up the view of the lake from his house.  Jonsered difficult to start when fully warmed up.  By quitting time we both were pretty well knackered and desperately in need of a cleansing, relaxing, cool-down swim.  While we were in the thrall of refreshment, Perry stopped by to drop off another generous assortment of veggies from his garden plus some succulent blackberries. Fearing the worst ‘cause the refrigerator has completely defrosted itself over the past two days, stuck the thermometer in Delores’ refrigerator and freezer.  Sure enough the refrigerator is at nearly ambient temperature and the freezer is hovering around 31 degrees, even with the thermostat set to maximum cool.  Am also getting very suspicious about the propane tank level gauge… it’s been showing half a tank all week in spite of copious use of the stove, oven, and hot water.  I look into the crystal ball and see $$$$ in my future.  Dinner over at Dan’s: steaks on the gas grill, Kingsley corn, one of my better salads (most of whose ingredients were from Lynne’s & Perry’s garden), and a couple of slices of that wonderful blueberry pie.  Night had fallen by the time dinner was done, so we decided to take Hopea Kanootti out for a spin.  Had to cut the paddling short when I discovered the old fashioned painful way that, after a day of slinging a chainsaw around, my broken rib just wasn’t in the mood for any more exercise.

2 August 2011

The wonder drugs were, indeed, wonderful, enabling an on-time transition from recumbent to vertical without the recent fuss and bother.  Liam Powers arrived around 9 am and was here until 2 pm installing the florescent light fixtures and another electrical outlet (for the garage door opener) in the shed lower level.  While he was stringing wires hither and yon, I got another course laid and cemented in three sections.  Dan came over for burgers on the grill and Kingsley corn; he brought with him wonderful summer squash side dish and a homemade wild blueberry pie. Need to remember to invite him over for dinner again REAL soon!

1 August 2011

Came very, very close to not being able to get out of bed this morning, which engendered a morning-long internal debate about four options: a masseuse, a chiropractor, a doctor, or a gun.  After laying and cementing another course of rocks in one section (missing the mark by ½ inch… close enough for government work), I began an hours-long tussle with the military health care system, culminating in an early afternoon conversation with the nurse for my primary care provider at DeWitt Army Hospital in Virginia.  She told me to get my rear-end to the nearest emergency room, pronto.  Was in and out of Middlebury’s Porter Hospital in 45 minutes with, hopefully, the prescription to cure my ills.  Better living through chemistry, that’s my motto!  Upon return to Fern Lake, laid and cemented another course on two more sections of the between-columns rock walls.