30 July 2018
Shlomo and I met Perry at his nearby job-site
first thing this morning and borrowed his electric hand planer. Using that handy device (tee, hee) slowly but
surely transformed the 2x12 bevel hack job into an acceptable looking end result. Then re-glued and added many extra lag screws
to three areas of the eastern 24′ mid-span beam as the tops of the two LVL’s
were spread apart up to ½″. Since the
strength of that beam depends on the two LVL’s being tightly bonded to each
other, figured I’d better fix that problem ASAP. Had lots more fun (again) shoveling and
raking level the west side of the barn foundation. Then started to backfill the electric conduit
trench on the house side of the stone wall, plus dig out the bottom of one of
the 4x4 posts that I want to move so that I can cut down the main electric
pedestal once the sub-panel is moved into the barn. Don’t recall this being done, but it sure
looks like the bottom end of that 4x4 has been encased in concrete. WTF, over!
Also the pedestal was put together with Phillips head screws… buried
deep. Let’s just say it’s a good thing I
own a Sawzall… and I’m not thinking kind thoughts about the guys who built that
structure. Ian Birkett will be sad to
hear this, but had to disassemble my trusty Craftsman radial arm saw (which has
served faithfully and without complaint for over 40 years, Ian’s opinion
notwithstanding) and, late this afternoon, took the motor and head to a
machinist for some minor repairs.
29 July 2018
Two of my pet peeves are (1) carpenters who
drive screws so deep that, as soon as the least moisture swells the wood, the
screw heads just flat disappear and (2) carpenters who just grab any old screw
in their pouch to put in a piece of wood instead of getting a handful of the
screws being used for everything else on the project. Do you sense a rant coming? First thing this morning went to convert the
ceiling joist trapezoid into a rectangle.
With some difficulty, removed the joist hanger (6 nails fastened into
the LVL, so holding very tenaciously).
Then went to take out the two screws holding the end of the joist to the
LVL. Both driven almost to China and no
matter what angle I held the impact driver bit, they just wouldn’t come
out. Grrrr… Used my knife to pare away the fibrous
overburden to discover that someone (not me) had used star-drive instead
of square-drive screws on this joist.
Double grrrr! After the joist was
moved and refastened, took out my frustrations by drilling more holes to
accommodate electrical wiring. Then I
decided to get artsy (big mistake!) by beveling off the ends of the two
2x12’s that will catch the top of the barn staircase. Only problem (other than that I’m an idiot
for even trying this) was that my trusty Skilsaw only cuts 2¼″ deep… and, of
course, the depth of two 2x’s is 3″, so you have to cut the bevels from both
sides. Obviously, there wasn’t a snowballs
chance that the four cuts (two for each bevel) would line up. So tried to fix the resulting disaster with
my jigsaw. Made thing even worse! Withdrawing from the field of battle with
tail between my legs, after lunch used the Kubota to roughly backfill the barn
foundation on the south and west sides, stealing fill back from the space
aliens. (They didn’t seem to mind…) Then had lots of fun (sic) raking the south
side smooth and level. That done,
decided the lake and sauna needed my attention more than the west side of the
barn.
28 July 2018
Put up a bunch more hangers on the ceiling
joists we hung yesterday, discovering in the process that we managed to create
another trapezoid by putting one joist on the wrong side of the mark. Also filled a few empty holes where joist
hanger nails should have been hammered in yesterday… Ended the day by drilling lots more holes in the
joists for electrical wiring runs.
27 July 2018
Sonny and Ty Zimmerman arrived shortly before
7; so much for my beauty rest! We
continued putting up the ceiling joists, getting all but the framing around the
staircase done before lunch. Sean came
by mid-morning to review progress. While
he was here, Sean used his clout to expedite the order I had placed with
Goodro’s this morning, as work was going to come to a screeching halt unless we
got some 2x12’s for the staircase header… 2x12’s I hadn’t ordered until Sonny
and Ty explained that the stairs would fall down without them. What’s the architect versus carpenter score
now? Sean also brought the news that
Goose Creek’s further efforts on the barn will be suspended until the week
after next. Perfectly
understandable. Though it’s a story too
long to relate here, those who have heard the local news know about the fire in
Cornwall last week that severely damaged a 7,000 square foot house… that Goose
Creek had just about finished renovating.
After lunch Sonny, Ty, and their cheap-labor assistant brain-stormed the
staircase header framing (the architect’s design didn’t pass muster… again!),
then built that critter. With black
clouds rolling in, we put away all nonessential tools and materials, then cut
and installed the ¾″Advantech® flooring for the 8′ x 12′ barn loft
area. With perfect timing, it didn’t
start to rain until the after-work adult restoratives had been consumed.
26 July 2018
Late afternoon, after the rain had abated and
while I was busy scavenging mud fill to put around the west side of the
barn foundation, Perry stopped by to see how the construction was progressing.
25 July 2018
No geese today.
In spite of that, accomplished quite a bit: finished putting in all of
the wall blocking (doing a much more professional job this time around), tidied
up the already-run electrical wires, and then put hangers on the east ends of
all the joists Sonny and I installed yesterday.
That latter job would have been a bit less frustrating if many of the
screws holding the joists to the 24′ LVL hadn’t been right where the joist
hanger toe nails had to go. Final score:
19 nails bent and pulled for 14 hangers installed. Sonny called at the end of the day to say
there would be no geese again tomorrow due to forecast heavy rain.
24 July 2018
Sonny arrived, per usual, at 7. We first put in all the cripples between the
top plate and the overhead door header.
As we finished that task, the Goodro’s truck arrived with most of what I
had ordered… and a promise (that was kept) to bring the other items later in
the day. Sonny and I then straightened
the east and west walls, installing the second top plate on all the walls as we
went… but forgetting until much too late that we had intended to shim those
plates so that they were perfectly level.
Checked with the laser level and, sure enough, there is a ¼″ elevation difference
between the northwest and southeast corners at the top plate level, a
difference that will have to be corrected when we cut the bird’s mouths for the
roof rafters. (The bird’s mouth is the
notch cut into a rafter so it sits down flat on the wall top plate.) In the midst of that activity, Jeff Many from
Green Mountain Door came by to scope out the framing preparatory to giving me
an estimate for the 8′ x 16′ overhead barn door. Found out that the Wayne-Dalton 8300 series doors
installed in the woodshed and house garages were made in China (boo, hiss!!!),
but there is a very similar overhead door made in Canada that is competitively
priced. We’re definitely buying Canadian
for the barn! Sonny and I then put in
all the west wall blocking. That is to
say, Sonny put in 11 perfectly aligned blocks in the time it took me to put in
3 very amateur-installed blocks.
Guess that’s why he gets paid the big bucks! After lunch, we put up the inverse flange
joist hangers on the west wall, then hung the 2x6 ceiling joists between the
west wall and the westerly mid-span 24′ LVL, straightening the LVL as we
went. By quitting time we both were in
desperate need of liquid refreshment.
After Sonny left (and I had mowed the lawn) there also was desperate
need for some lake time.
23 July 2018
Luther and Sonny arrived promptly at 7. A quick inspection determined that somebody
(probably me) put the top of the east wall end stud on the wrong side of the
mark, i.e. 1½″ out of position. With two
screws pulled and a tap-tap with a hammer on the stud, the wall became a
rectangle. Miracles do happen! With an assist from Dave Todd (across the
street neighbor who was over to check on progress), the fourth 14″ x 24′ LVL
was quickly hoist into position. Then we
put up the two 16″ x 16′ 7″ LVL’s that form the overhead door header. Piece of cake!!!! While Sonny and Luther checked to see if the
walls still were plumb and straight, I installed four king studs that secure
the 24′ LVL’s laterally, but that we had left out when we built the north and
south walls so we could slip the LVL’s into position. (Pat-on-the-back-note: We ended up with exactly
the right number of rough cut 2x4’s needed for the wall studs. Talk about luck perfect
planning!) Sonny ventured forth to scavenge
staging from other Goose Creek work sites.
As soon as Sonny (or should that be: Sunny?) left, it started
raining. Luther put up the bottom top
plate over the garage door and laid out the cripple positions while I chopped
“scrap” rough cut 2x4’s into the length needed for those cripples. (For non-carpenters: cripples are short wall
studs that distribute the top plate load down to a door or window header.) Awaiting Sonny’s return and thoroughly
drenched, Luther and I took shelter in the woodshed and did a
back-of-the-envelope design for the barn staircase. At 11:30 the prodigal returned, was quickly
unloaded, then, with rain continuing unabated, he and Luther departed for dryer
climes, i.e., lunch at Rosie’s Restaurant courtesy of the Sean (aka: The Boss). At 2:30 the sun came out! So out to the barn went I, swept the lake off
the floor, and started putting in wall blocking. Got three blocks in when rain started
again. At 4 the sun made an encore
appearance, so out went I once again.
This time I didn’t even get all the water off the floor before the next
deluge. So spent the rest of the
afternoon checking over the staircase design, catching a few errors, and
calling Goodro’s repeatedly to add items to my order for delivery tomorrow.
22 July 2018
Made a run to Burlington to raid Lowe’s and Home
Depot for sundry hardware items. After
returning mid-afternoon, finished drilling electrical wiring holes in
already-installed wall studs. Perry came
for our weekly sauna, which facilitated a valuable discussion about how to best
install the barn ceiling joists so that they also can serve as collar ties for
the walls. (Tech Speak: when the roof
has many, many tons of snow on it, the downward pressure wants to squish
(that’s a carpentry term) the building flat by pushing out the tops of the
walls. Bad juju! While joists normally experience a vertical
load, collar ties keep the wall tops from moving outward and thus experience a
horizontal pulling load. So, in the
barn, we need to attach the joists to the 24′ LVL’s and the east and west walls
in such a manner that they can withstand both vertical and horizontal
loads. Just in case you were wondering,
the 24′ LVL’s are the collar ties for the north and south walls. See, that wasn’t so hard…)
21 July 2018
With a few minutes to spare before moving on to
other Saturday chores, started to put in the wall blocking. First block fit snug at the bottom of the
east wall but was an inch too short at mid-span. Standing back a bit, was obvious that the
wall was a trapezoid instead of a rectangle.
So stopped the blocking install and instead spent an hour drilling holes
in studs for the electrical wiring runs.
20 July 2018
Sonny and Luther arrived at 7. We got straight to work framing the rest of
the walls. By noon the north, west, and
south walls were done, with only the gap above the east wall garage door opening
needing to be framed. The two geese then
straightened and plumbed all the walls, attaching bracing in each corner to
hold everything in position. That done,
we put the first 14″ x 24′ LVL on the Kubota’s forks and hoisted it skywards…
discovering that at the tractor’s highest reach the LVL was 3′ lower than it
needed to be. But, strong and clever
guys that we are, the LVL was quickly and easily muscled into position atop its
supporting jack studs. A second LVL soon
followed, which was glued and screwed to its sister. A few minutes later, the third 24′ LVL was in
position. All was going too smoothly… I was out fetching the fourth LVL when I
looked back at the barn and saw, quite clearly, that LVL numero tres was not
parallel with numeros uno and dos. After
a bit of head scratching, we discovered that an unnamed person (what happens in
the barn stays in the barn) had cut one set of jack studs for the south wall 3⁵⁄₁₆″
longer than for the north wall. Why 3⁵⁄₁₆″? Because that is the offset between the beam and
the base on the laser level being used to ensure all the walls, jacks, and
openings are the right height. Nothing
for it but to get out the Sawzall and cut through the hidden screws holding the
high end of the LVL in place, then cut off the offending too tall jacks, and
lower the LVL down to the proper level.
On that note, it was Miller time, followed shortly thereafter by lake
time.
19 July 2018
Luther and Sonny pulled in shortly before
7. As they got to work continuing the
north wall framing, I boogied to Green Mountain Electric Supply (AWG 12-2 wire
and ½″ EMT conduit), Goodro’s (more PL Premium adhesive and 2x6 PT lumber), and
Carrara Concrete (¾″ washed stone). Even
though the bed wasn’t full, had to stop the bucket loader putting stone into
the bed of the Tacoma when the front wheels looked to be in danger of leaving
the ground. However, was able to steer
the truck back to Fern Lake by touching the brakes at regular intervals. There, I looked at the load slip. Seems I was carrying 2,660 pounds of stone in
a truck rated for 1,150 pounds. Ooops! Then, while Sonny and Luther admired my sweat-soaked
physique prowess, I spent a fun-filled hour shoveling all that stone out of
the truck and into the trenches alongside the walls. The Goodro’s truck came by mid-afternoon
bringing another thousand dollars worth of lumber. By quitting time we had finished framing the
north wall and ⅔ of the west wall. After
the guys left, used the Kubota to backfill around the west and south walls,
discovering that space aliens have made off with a lot of the dirt needed to
complete that process. Hmmm…
18 July 2018
Luther Corcoran from Goose Creek got here at
8:30 and his partner in crime, Sonny Torrey, pulled in at 11. Was great to see them again as both are hard-working
and very experienced master carpenters… and just plain nice people! Before Sonny arrived, Luther and I went over
the building plans, location of materials, then double checked the concrete
wall lengths and “squareness”. The measurements
weren’t as bad as what Chree and I found the other day but, that said, the barn
walls will be officially 24′ 3/16″ long. Then we got to work laying out and installing
the pressure treated 2x6 wall sole plates.
After lunch we first built and erected the framing for the two short
walls that will be either side of the overhead door and then the first section
of the north wall. Because Luther wanted
to use a two-bottom-plate construction technique (which, after pondering, made
a lot of sense), the barn will be 1½″ taller than designed. That change also raised the window sills
½″. In reviewing that impact, the
not-so-brilliant building designer realized that there will be no room under
the windows for the electric wires that need to feed the outlets that will be
in the concrete walls centered under the windows. Fortunately, Luther quickly figured out how
we could cut a channel for the wire in the upper bottom plate. Goose Creek, 1: Architect, on probation!
17 July 2018
No Goose Creek folks today ‘cause of forecast
rain. In fact it did sprinkle a bit this
morning, but the major deluge (1″ in 20 minutes) didn’t hit until after
quitting time. C’est la vie! Spent some quality time in the shop this
morning making the window jack studs. In
order for the window rough openings to be the correct height and width in the
locations I want them, those jack studs need to be exactly 48½″ long and 111⁄16″
thick. Enter, stage left, my thickness
planer. In the course of making those
jacks, discovered three things: (1) the Orkin pest control treatment of the raw
lumber drying in the wood shed was decidedly less than effective, (2) in less
than two months the rough cut hemlock 2x4’s have dried to a considerable degree
and are reasonably straight (J!), and (3) my 40+
year old radial arm saw finally needs some professional repairs if I want it to
cut straight and true again. Until I was
chased indoors by the deluge (see above; also a whiskey and ginger was calling
my name), did some more work on the wood walkway this afternoon.
16 July 2018
A quick trip to Goodro’s made me the richer by
one 6″ J-bolt (the J portion of which soon was cut off, leaving a ½″ galvanized
threaded rod 5½″ long), some 3,200 psi Gorilla® glue epoxy, and a
new ½″ concrete drill bit… plus the 2½″ star-drive wood walkway screws that I
ran out of yesterday. Literally a few
minutes after returning to Fern Lake, the missing sole plate tie-down bolt had
been drilled and glued into place. Doing
the math, the pulling force that that bolt should be capable of withstanding is
more than 7 tons. Thing that’ll do! Then got out the Kubota and backfilled and
graded the north and east sides of the barn foundation.
15 July 2018
Even though it’s her favorite (sic) job, somehow
Chree had an important appointment in Middlebury this morning when time came to
tar (but not feather) the below-ground portions of the barn south and west
walls. Used a paint roller this time,
which worked surprisingly well; only got a gallon or two on me while applying
the rest to the walls. With perfect
timing, Chree got back just as I was finishing.
Checked the position of all the conduit and tie-down bolts protruding
from the tops of the walls to verify there would be no interference with wall
studs. Discovered that the Long Ridge
crew had left out one of the tie-down bolts!
Merde alors!!!! Also discovered
that I had cleverly placed the conduit for the embedded wood electrical outlet
boxes about ½″ too close to their neighboring studs. Double merde with more alors! On a positive note, finished moving the
planks for another 40 feet of the wood walkway (whereupon I ran out of screws),
enjoyed several dips in the lake (whose temperature now is a balmy 80° F), and
took an extra long sauna.
14 July 2018
A showery Saturday, so spent a few hours meticulously
reviewing all the barn construction plans and calculations, plus drawing an elevation
view for the north wall. Too exciting
for mere words!
13 July 2017
Friday the 13th started out with me
having just barely (literally and figuratively) rolled out of bed when Brett
and the Goodro’s trucked pulled in, bearing the 2x6 PT lumber needed for the
barn sole plates. Dressing quickly, got
out to the job site just as Brett finished unloading. Darn the luck! After errands in Middlebury, finished parging
the dirt-side south wall / floor slab seam.
Chree having gone to Rutland shopping, the parging went much better with
lots of inappropriate verbal “encouragement”.
12 July 2018
Troy and the Goodro’s big boom truck delivered $4,700
worth of barn building materials mid-morning.
The first thing we’re going to need from that delivery are the 2x6x12
pressure treated (PT) lumber that will become the wall sole plates, so I looked
through the piles to make sure those boards hadn’t gotten buried under
something heavy, i.e., the monster LVL’s. Finding no 2x6 PT, I asked Troy where they
were. “You ordered 2x4 PT”, he
said. “Oh, oh”, says I, (or words to
that effect) scurrying into the house to get my list. Sure enough, I had ordered 2x4’s,
knowing full well that we need 2x6’s. So
Troy loaded the 2x4’s back on his truck and promised to send out some 2x6’s
before Monday. After Troy left, finished
breaking off the form ties on the dirt side of the building. After lunch, mixed up some hydraulic cement in
anticipation of patching a few areas on the inside of the walls where the
person tapping the forms didn’t do a very good job of getting the concrete to
flow. Who, me? Now, you should know that working with
hydraulic cement happens to be absolutely miserable, ‘cause it sets in less
than a minute… literally. So you can
only make a teensy amount at a time, then by the time you scamper over to where
it needs to be applied it’s getting hard already. Worse yet, I discovered that the outside seams
between the west and south walls and the floor slab (48 linear feet) are
in pretty rough shape, so those seams need to be completely parged with that
cement. Many, many batches got the west
wall seam done and me worn out. Chree
and I checked the poured walls for square, plumb, and level… twice. The south wall is perfectly plumb and level
and the same length as the east wall… both being ⅛″ too long. The west wall is sort of plumb and sort of
level, but ⅛″ too short. So far, not too
awful bad. However, the north wall,
which is only 11¼″ high, is out of plumb by ¾″ over that short height and is ⅜″
too long. Not good! And, because the concrete walls aren’t the
same length, the diagonals (which are used to check that the foundation is
square) differ by ⅞″. Looks like we’ll
be having some “fun” with the carpentry!
11 July 2018
Started work taking apart the concrete forms at
the very reasonable hour of 8:30 (that last phrase for Sean’s benefit… keep
reading to find out why). While in the
midst of removing the 2x12 forms, stakes, and other wood paraphernalia, the man
himself arrived. We spent an hour going
over the barn building plans… and catching up on happenings over the past two
years. Sean found nothing wrong with the
plans (whew!). We also talked about the
scope of work Goose Creek will do and who Sean will send down to help with the
carpentry… hopefully starting next Monday morning. Then the bad news: Goose Creek still starts
work at 7 am. Gaak! So much for the no-alarm-clock retired
life! Soon after Sean left, just as I
was about to start snipping the form ties (they have to be cut to release the
pressure on the steel rods that hold the forms in place so that said rods and
forms can be removed), Victor and Karl arrived… about 3 hours before I was
expecting them. With the three of us
working, the rest of the forms came down quickly. About noon-thirty, Larry and Kyle also pulled
in to help finish loading all the Long Ridge material onto the trucks. By shortly after 1, the concrete crew was
gone and I started breaking off form ties. (Once the forms are off two very
sharp (I have scars to prove it) metal ends protrude from the concrete; those
have to be broken off flush with the wall using a hammer… and a bit of
technique, which I learned during the house construction.) After an hour of hammer swinging all the ties
on the inside walls were gone… and my right forearm was completely
cramped. Guess I’d better add swinging a
hammer side to side to my gym workout routine!
Finished the day lying in the sun sucking down a G&T cleaning
up stray concrete and generally getting the floor slab clean enough to eat
off. Mr. Type A strikes again! …and, yes, the G&T and BBQ chicken
(cooked over a wood fire) did go down rather easily come dinnertime.
10 July 2018
Victor, Karl, Kyle, and Ryan pulled in about
1:30, followed shortly thereafter by Larry and a Carrara mixer bringing 3 yards
of 3,000 psi concrete. Even though the
concrete had had extra chemicals added to make it flow more easily with less
water (concrete needs water to activate the reaction that causes it to get hard,
but too much water weakens the resulting structure), and the crew was using a
vibrator to liquefy the mix, it still was so stiff that Larry had to have more
water added, twice, to get it to spread out in the forms. My job (besides taking pictures and staying
out of the way) was to beat on the forms with a hammer to get any air bubbles
away from the wall surface, i.e., more hammering = smoother walls. Once the 28 tie down bolts were inserted and
the tops of the walls had been troweled smooth and level, Larry and his guys
left. Final step for the day was to
inscribe Δ□Ο and 2018 into the fresh concrete.
9 July 2018
Worked most of the day on the wood walkway,
getting the next section taken apart and put back together, which brings us
down to the aptly-named half-way bench.
My knees may never be the same.
Chree and I also screwed the wood electric outlet boxes to the inside of
the barn concrete forms.
8 July 2018
Removed all of the wood walkway boards from the
10th section (the one closest to the dock) and replaced them with
the new boards that Goodro’s delivered.
The new boards were put in tightly butted to each other (the way the
whole walkway should have been built!) so that as they dry out and
shrink, the proper gap will be left between boards. Am using the removed (and well seasoned)
boards to fill in as needed on the other sections of the walkway, which keeps
everything looking uniformly aged.
Finished moving and reattaching all the boards in the 4th
section of walkway… then Shlomo and I went for a well-deserved swim.
7 July 2018
Larry, Victor, Karl, and Trey got here just
before 8:30 (this being Saturday morning, they allowed themselves a late start)
to form the two 11¼″ curbs (north and east sides of the building) and the two
31½″ “walls” (south and west sides – where the barn juts into the side of the
slope). The Goodro’s truck arrived at 9
bearing 10 pieces of 5/4 x 6 x 12′ pressure treated lumber for the wood
walkway. I had the truck go around to
the backyard to unload, thereby testing the strength of the final section of
wood walkway put in back in May. The
walkway moved not a bit as the truck drove over it (twice)! Meanwhile, back at the barn-build site, all
was going too smoothly (have we heard that phrase before?), with most of the
inner walls in place, when Larry remembered that he needed to put bentonite water
stop in the bottom of the forms. That
material swells in contact with water, thereby sealing the seam between the
curbs / walls and the concrete slab.
Nothing for it but to take down the inner wall forms, lay down the water
stop, and put the forms back up. Did I
mention that the hardest part of putting up concrete forms is aligning the form
ties with the inner wall form tie holes?
There’s a real trick to that process but, even though Larry is a master
former, it’s still a hard job. As the
forms were going up, Victor checked the diagonal and found that they were ⅟₁₆″
out of square. Not too shabby!!!! By just after noon the forms were ready for
concrete, minus the wood electrical outlet boxes that I need to install inside
the two walls. Spent the afternoon
moving wood walkway boards to achieve the optimal 3/16″
spacing, getting the third section finished.
6 July 2018
After seven days of watering, pulled off the
HydraCure® membrane to find a beautiful (and uncracked)
concrete slab. Using my angle grinder,
cut the rebar pins down to their proper sizes, i.e., 9½″ for the curbs and 29½″
for the walls. As new concrete does not
bond with concrete that has already set, those pins will keep the curbs / walls
from moving laterally (or vertically, for that matter) on the floor slab. After a brutal week of 90°+ air temperatures,
the lake water temperature is up to 84°, the warmest that I have ever observed.
Subscribe to:
Posts (Atom)