4 February 2016
Ran
down to Brandon at crack of dawn, getting to Aubuchon Hardware just as they
opened. Unfortunately, they only had two
of the 4″ round ceiling boxes I needed.
Rats! Sonny and Doug spent a
couple of hours sheathing the area under the stairs with plywood so that Steve
could start installing the cold water manifold and associated equipment in that
space. Then the sheet rocking duo went
back to putting up ceilings. With many
distractions, they got part of the living / dining room done today. Steve continued the plumbing rough in for
part of the day. Due to some confused
communications, the floor under the walk through closet will be in the heating
zone controlled by the study thermostat rather than (as was intended) in the
zone controlled by the master bedroom thermostat. Oh, well, at this point it is what it
is… Sean was here for much of the
morning to talk about the next month’s work schedule. Jim and James Ploof showed up unexpectedly
mid-morning to see if I wanted any work done now that the ground is again thawed. Answer: yes… and they’ll start tomorrow. Brian Thomas (Black Diamond Builders, the
insulation subcontractor) was summoned when Sean and I couldn’t agree on how to
insulate the area where the kitchen flat ceiling transitions to the sun room
vaulted ceiling. Brian was on-site
within the hour and successfully mediated the discussion. The end result will be that the entire main
level ceiling will be insulated to R-60 vice R-39 over the sun room and R-60
elsewhere. Me likey!!!! Me checkbook, probably not so much. Goodro’s truck showed up mid-morning with
vast quantities of R-15 Roxul insulation and the 20-minute fire-rated door that
will separate the garage from the mud entry.
Tom and I continued work on the electrical wiring. He linked all the smoke and smoke / CO
detectors together with 18-2 wire so that, if one goes off, they’ll all go off. Tom also made up many more of the electrical
panel connections, discovering in the process that the previously installed
utility room circuit breaker not only was in the wrong slot, but couldn’t be moved
to its proper location because the wires were too short. Solution: the utility room shall hereafter be
known as the mechanical room… a term that everyone was already using anyway. Late afternoon I made a mad dash into
Middlebury to retrieve 5 AFCI and GFI circuit breakers that Glen Peck
graciously is selling to me… saving me another run north. Also stopped for my daily electrical material
fix at Green Mountain Electric Supply.
Over to Marty & Merry’s for another fabulous stuffed salmon dinner.