26 July 2014
Spent much of the day
cleaning / tidying the building site and making sure everything is protected
from the rain forecast for the next two days.
Put on all the rest of the joist hangers for the purlins that have been
installed. (Note: there are a few purlins that can’t be installed until the
chimney is built.) Perry came over late
afternoon and we spent a couple of hours playing around with creating a
triangular wood cap to go on top of the hip rafters so that the roof sheathing
will be supported where it goes around the corner at each hip.