27 August 2013

Surveyed the walkway so I could accurately draw it on the site plan that has to be submitted with the Building Permit Application for the Dock Building and Walkway.  Got that done just as the Fyles Brothers truck arrived to deliver 7.2 gallons of propane (all that had been used since the last fill up at the end of May).  Then started ripping old deck planks into 2 x 2½ ″ boards that will become kick plates for the 195 feet of the walkway that still need that component.  Was just finishing up that task when the FedEx truck arrived at 12:45 with the tools Mr. Booby left behind in Virginia.  Thus was able to smoothly transition to installing said kick plates onto the section of walkway between landing #7 and the waterfront.  Finished that section, then cut and installed the mounting board for the lower transformer, just before heeding the siren call of the warm and placid waters.  Swam across the lake and back without pausing to rest on the western side.

26 August 2013


Met with Kate Briggs as planned this morning.  She issued, on the spot, our building permit for the Wood Shed, which we have to prominently display for ten days. On a more contentious note, Kate INSISTS that our wood walkway is NOT a handicap access ramp (‘cause, she says, such a ramp can only provide access to a dwelling) and that the walkway is a “structure” in spite of the fact that it is not among the items listed in the Zoning Bylaws structure definition.  We agreed to disagree on both those points.  Compromise solution: I am adding the walkway to the Building Permit Application that is being submitted for our proposed dock building (that needs a setback waiver) so that the Zoning Board of Adjustment can consider them as a package.  The ZBA hearing will be on 24 September.  While I was meeting with Kate, the Glassner’s former handyman came in to inquire about building a dock for one of his clients.  Kate said that so long as the dock is a temporary structure, i.e., capable of being removed from the water by “two strong men”, then no permit is required from the Town.  I don’t think Kate has any idea what even a small wooden dock weighs.  The design I am submitting with the dock building / wood walkway application includes the 24 x 12 dock I intend to build, constructed to meet the State requirements for a dock for which no State permit is required.  As I was leaving our meeting, Kate expressed regrets that I’m not a full time resident and thus not available to help with rewriting the Leicester Zoning Bylaws… apparently an ongoing project.  Methinks a blessing in disguise!  Returned to Fern Lake, I put the Ranger into winter storage, i.e., disconnected the battery and called USAA to modify the insurance coverage. Also called the Storm King portable generator manufacturer to find out why the electric start no longer works.  Get this: the generator does NOT recharge the starting battery when it is operating, so a few hundred starts later, the battery is out of juice.  What idiot designed that system????  Planned to slow cook some spareribs all day.  Opened the oven to ignite the pilot light and found… yes, the mouse (mice) had removed all of the rest of Dolores’ insulation and made another Taj Mahal-quality nest therein.  Fetched the shop vac to remove said nest and found a baby mouse cowering in the back of the oven.  On my way into Middlebury to spend money do errands, I dropped off the baby mouse at the Silver Lake parking area where I’d put its mother(?) yesterday.  Back at Fern Lake, discovered some home-grown tomatoes on the dinette table.  Also discovered another baby mouse on the kitchen floor, obviously having escaped the hot oven.  So called Perry to say thank you and see about going over to use his printer (Kate wanted a picture of the wood walkway included in the Building Permit Application package.)  Got to Perry’s, by way of the Silver Lake Parking Lot, again, only to discover that I’d put my thumb drive, instead of the similarly-sized Ranger truck key, in my computer case just as I was leaving the RV.  So made the roundtrip to Fern Lake, again, stopping at Kingsley’s Farm Stand to pick up some gift corn for Perry.  Perry gave me an envelope as I was departing, with instructions not to open it until back at Fern Lake.  Inside I found five pages of synonyms for the word “idiot”.  Personally, I’m kind of partial to “booby”…

25 August 2013

Now you see them, now you don’t.  Backfilled the conduit trench (mostly by hand, which was an excellent workout), then used the backhoe to dig a nice deep trench next to the steel pole (and huge concrete base) for the Glassner’s old satellite dish, toppled the critter over, and laid it to rest forevermore.  In lieu of flowers, the family requests charitable donations made out to the Christine Tarrio Perkins Trust.  Kate and her houseguest took Hopea Kanootti for a leisurely spin around the late at noon.  While they were out paddling, discovered (no surprise) that the Ford Ranger battery also was flat, so jumpstarted that truck with the Tacoma.  After letting the Ranger idle for a half hour, found that the battery is still flat.  Merde, alors, if you’ll pardon my French.  Hauled the tandem axle trailer out of its parking spot to check that all was in working order for its upcoming trips.  One marker light inoperative, but everything else seems fine. Made an appearance at the annual Lake Dunmore / Fern Lake Association picnic held at Camp Songadeewin.  While there, introduced myself to Kate Briggs, the Leicester Zoning Administrator, and set up an appointment to see her officially in her office tomorrow morning.  Another delicious dinner and delightful evening at Marty and Merry’s, complete with pictures of Chree’s and my first grandchild, Devin Douglas Perkins.



 


25 August 2013

Now you see them, now you don’t.  Backfilled the conduit trench (mostly by hand, which was an excellent workout), then used the backhoe to dig a nice deep trench next to the steel pole (and huge concrete base) for the Glassner’s old satellite dish, toppled the critter over, and laid it to rest forevermore.  In lieu of flowers, the family requests charitable donations made out to the Christine Tarrio Perkins Trust.  Kate and her houseguest took Hopea Kanootti for a leisurely spin around the late at noon.  While they were out paddling, discovered (no surprise) that the Ford Ranger battery also was flat, so jumpstarted that truck with the Tacoma.  After letting the Ranger idle for a half hour, found that the battery is still flat.  Merde, alors, if you’ll pardon my French.  Hauled the tandem axle trailer out of its parking spot to check that all was in working order for its upcoming trips.  One marker light inoperative, but everything else seems fine. Made an appearance at the annual Lake Dunmore / Fern Lake Association picnic held at Camp Songadeewin.  While there, introduced myself to Kate Briggs, the Leicester Zoning Administrator, and set up an appointment to see her officially in her office tomorrow morning.  Another delicious dinner and delightful evening at Marty and Merry’s, complete with pictures of Chree’s and my first grandchild, Devin Douglas Perkins.




24 August 2013


Took the Kubota down to the waterfront first thing to finish digging the power / water line trench from where Alex and I left off in early July to the end of the wood walkway.  Maneuvering the tractor onto the slope from the upper work road was more than a mite hairy.  Even with the seatbelt fastened, I thought I’d have to stop and get clean underwear on a couple of occasions before I got situated.  Then, trying to dig the trench while pointed uphill, the Kubota kept trying to do a wheelie… which was a tad disconcerting until I solved that problem by filling the front bucket with rocks.  Trench dug, assembled the next 40 feet of conduit and pulled the line through with no problems.  [The line will be used, eventually, to pull the electrical wires through the conduit.]  Went to feed the line through the very last section of conduit and the $%#@!!! thing came apart.  Only thing I could do at that point was to pull all the line back out of the conduit, suck a string through, and use the string to re-pull the line.  Kate, up for a weekend of R&R, graciously came over to help feed the string into the upper end of the conduit while I created suction at the lower end using the shop vac.  Worked just as advertised.  Told Kate I could do the rest myself… oh, foolish me!  Was re-pulling the line with only moderate difficulty when… the string broke!  So, what should have been a 15 minute job took me over three hours… but at the end of a very frustrating day there is a line all the way through the conduit once again.  The lake level is 8″ below the top of the dock and the water temperature is 77°.  Can’t decide if the swim after work or the lager and wood-fired T-bone for dinner was the highlight of the day.

23 August 2013

Another mouse, recently residing in the utensils drawer, has been given a new home at the Silver Lake parking lot.  Met with Joan Donahue, Esq., in her office to discuss questions about the applicability of the Leicester Zoning Bylaws to the various construction projects (completed, ongoing, and future) that are the subject of these ramblings.  On the way back to Fern Lake stopped at the Middlebury Hannaford to procure several food items that got left in Virginia because I’m an idiot.  Then started to reinforce the plastic milk crate mounted on the Kubota for tool carrying (it wasn’t holding up to the abuse it was getting) and discovered that I’m even more of an idiot that I thought… except that apparently even such simple thoughts are beyond my ken, i.e., I also left both cordless drills, my drill bit assortment, and my hacksaw behind in Virginia. On a positive (????) note: I now have TWO full bottles of Black Label and FOUR tubs of butter here in Vermont.  Do you suppose the Scotch will counter-balance the cholesterol?  Faked repairs to the milk crate with my monster hammer drill and a ship auger bit while Tasi was busy in Virginia getting a $50 FedEx shipment together.  Spent most of the afternoon filling out Leicester Building Permit applications and doing the requisite drawings (site plan, floor plan, and elevation) for the (already built – oops!) Wood Shed and (wanted to build this summer but that ain’t gonna happen) Dock Building and Sauna (that will need a setback waiver from the Zoning Board of Adjustment).

22 August 2013

Left Springfield at 0600 and set a new land speed record to Baltimore – 3 hours 25 minutes, for an average “speed” of just over 20 mph for that leg of the trip.  Finally got to Fern Lake at 1700, completely strung out.  We had emptied the ice cube trays when we left in July, so had to drink the requisite restorative beverages neat. What torture! Good news: 1,600 mg of Naproxen taken just before departure kept the sciatic nerve pain in check almost all the way.  Bad news: Dolores is up to her usual tricks, AGAIN!!!!  Starting battery COMPLETELY flat.  Only took me 2½ hours to remember that the RV coach batteries can be cross-connected to the engine starting solenoid, i.e., the RV has the capability to jumpstart itself.  That done, Dolores condescended to start so that I could extend the slide-out.  Lots of mouse “signs” in the usual drawers… looks like they found out that the cat has been away for six weeks.