19 April 2016
Sonny and Brandon
continued casing the window interiors. Sonny
left at noon and Brandon at 3 due to other commitments. Brandon also built and installed the trim for
the master bath pocket door. Tom started
laying slate in the coat closet, cedar closet, and wine cellar nook. He also retiled the area in the master bath
shower where the water wasn’t draining properly. Roger Desabrais from Desabrais Glass stopped
by early afternoon to measure for the glass door and half wall that will form
one side of the master bath shower enclosure.
He also measured for the glass knick knack shelves that will be
installed in the upper hall. I spent the
day trying to catch up on construction finances. What a thrill!