Put the second (and final) coat of paint on the
barn’s exterior trim. Other than
installing two outdoor spotlights high on the east wall and having Tammy Walsh
build some gravestone steps for the people door, the barn is officially
done. (Hold that thought!) Chree headed to Maine to visit her parents
while I hooked up the trailer and schlepped up to Lowe’s in South
Burlington. Among many other items,
procured the two spotlights for the barn.
Also bought a ton (literally) of Black Jack Drive-Max 1000™ driveway
sealer (40 buckets @ 52 pounds apiece), hence the trailer. The cash register clerk neglected to charge
me for 39 of those buckets, which, fortunately, I caught before leaving the
store. Now I may not be too good at
mental math, but when the bill is $1,000 less than expected, even I can tell
something ain’t right! Started to
thunderstorm just as I left South Burlington and was threatening the same upon
arrival Fern Lake. So, in a rush, tried
to back the trailer into the barn before first removing the Kubota. Let’s just say that the trailer now needs a
new sidelight, the south-side overhead door trim is all torn to hell (and back
again)… and I got wet anyway.
30 July 2019
Steve came over at 2:30 and we took apart the
house front steps, which had pretty much fallen apart from settling due to not
having a solid base established when they were built back in mid-August
2016. Good thing Steve is strong, ‘cause
them gravestones ain’t getting any lighter as they age. Took us 45 minutes (in 90°+ heat!). Only 6 of the 18 stones that had been “permanently”
glued together with PL300 construction adhesive were, if fact, still glued
together… and a little “persuasion” from a cold chisel and my big pry bar soon
rectified their reluctance to separate.
29 July 2019
Steve Ingram here at 10. In a couple of hours, we put up the 1x4 Koma®
trim at the top of each wall. After
Steve left, moved the staging around the barn one more time, lightly sanding
the newly installed trim and the vertical corners, then caulking the seam
between the trim and the soffit. The
lake sure did feel good when that work was done.
27 July 2019
Out early to remove the temporary (since last November)
covering over the cupola base (the hole and associated structure at the top of
the barn roof where the cupola is to rest).
Also swept copious slippery pine needles off the metal roof. At 9, Mike & Pikey Many, Steve Ingram and
his good friend Hank Prensky, and Jordan Ahnquist (Kate’s boyfriend) all
arrived. In very short order we hoisted
the cupola (using the Kubota’s forklift) to the top of the staging, and then lifted
and slid it (manually) from there to the top of the barn. Easily done with enough beef! The cupola fit over the base absolutely
perfectly… almost like it had been designed that way! Even better, only two of the eight tie-down
bolts needed any “encouragement” to slide into position. Once the staging was down and everyone else
was gone, I installed the flying pig weather vane on the cupola peak. Then, at exactly 12:58:48 pm, when the sun’s
azimuth was 180° true (i.e., due
south), I aligned and locked into position the weather vane’s directional
indicators. In the afternoon, with some
help from Chree, I cut 45° bevels in the ends
of the 1x4 Koma® trim that will be installed on Monday… the
penultimate step to finishing the barn. Marty, Merry, their daughter Heather,
her daughter Gabby, Kate, and Jordan came up for drinks and shrimp on the barbie…
plus some chicken wings, and dogs, and…
Don’t think anyone wanted dinner after those “appetizers”.
26 July 2019
Put a coat of Behr Premium Ultra®
Pure White paint on the barn corner vertical trim and the 1x4 Koma®
trim. Put a section of aluminum ladder
on the south side of the barn roof to allow safe walking access to the peak
from the roof edge, and also serve as a “track” to slide the cupola up. Late afternoon, went over to Mike Many’s to
help load up his truck with staging, then the two of us erected the same on the
south side of the barn (where there is the least distance from the ground to
the roof edge). Proved that the Kubota’s
forks raise high enough to reach the top of the staging.
25 July 2019
The barn concrete floor being completely dry
(finally), got the seven pieces of 1x4 Koma® trim that I’ve been
storing since last summer ready for painting.
Much easier to put a first coat on those pieces with them laying flat on
saw horses than once installed at the top of the exterior walls. Calculated that I won’t need one of the 18
foot pieces of Koma. Riiiight!!!! Maybe I shouldn’t be in a rush to return that
piece to Goodro’s for credit… After putting
the trailer and snow blower back inside the barn, moved the cupola into the
barn as well so that I could put on the final top piece (a small piece of lead
that had to be trimmed to fit) and the base for the flying pig weather vane.
24 July 2019
While waiting for the concrete floor sealer to
dry, sanded the four exterior Koma® corners preparatory to painting
them later this week.
23 July 2019
Stopped by Goodro’s on the way back from
Middlebury Fitness this morning only to find that Tim Comb’s is on vacation… so
unable to coordinate having the Goodro’s boom truck hoist the cupola into
place. Murphy’s Law! Late afternoon fetched the cupola back from
Mike Many’s house / shop with the Kubota.
Looks great! Arranged for Mike,
Pikey, and Steve Ingram to help manually hoist the cupola onto the top of the
barn this coming Saturday morning.
Notice the positive thinking!
22 July 2019
Mike Many told Chree (during her morning
perambulation) that the cupola metal roof is done. So called Mike this afternoon to arrange a
retrieval time tomorrow. With the
relative humidity finally below 70% (it’s been at 98% for the last three days),
put the second (and final?) coat of silane sealer on the barn concrete floor.
19 July 2019
By noon the barn shingling was D∙O∙N∙E,
done! Which is not to say that the barn
is finished; there still is much trim that needs painting and one final run of
1 x 4 Koma® trim to be attached at the top of each wall. Not to mention that the concrete floor needs
another coat of silane sealer. Oh, yeah,
there’s also a cupola down at Mike Many’s that belongs on top of the roof. When the stapling was done, the air
compressor was behaving itself (a small miracle, that) and there were 74 (about
a half box) of full-length shingles left over (53 in the 3½″ to 4½″ range and
21 in the 7½″ to 9″ range), which equates to ≈ 13 square feet of coverage at a
5″exposure. There also are two boxes of scrap
shingles that will make either lovely wood fire kindling or just a great
bonfire. I’m leaning toward the latter… Spent the afternoon putting away tools, cleaning
up the mess inside the barn, removing everything from the barn’s concrete floor
(trailer, tractor, snow blower, BBQ grill, etc.), then power washing said floor. What fun!
15 July 2019
The lake temperature is a balmy 78° F and the lake level
is 1½″ below the top of the dock. Put on
another 17 square feet of west wall shingles today, every one of which had to
be cut to length and, often, to the width needed for a particular spot. Only one more course to go!!!! That equals 9.6 square feet… or approximately
55 shingles of various widths. The good
news: there are somewhat more than 100 usable shingles left.
The bad news: at least half of those shingles are between 3¾″ and
4¼″ in width… not a size that is used a lot.
Stay tuned for the exciting finish!
14 July 2019
Sunday morning chores consumed, surprise,
surprise, the morning. Got one more
course on… the last one that uses full length shingles. Started on the next course, the shingles for
which all have to be cut to exactly 15½″ long.
(Out of the box they all are ±15¾″ long and, yes, that ¼″ is critical to
how the wall will breath.) When the
siren call of the sauna became too overwhelming, another 12 square feet had
been fastened to the west wall.
13 July 2019
Slow going today as I had to “create” (one at a
time, down in the shop) 3″, 5″, and 6″ sized shingles from the plethora of 8″+
shingles on hand, plus pawing through and resurrecting pieces from the box of
flawed shingles rejected when working on the other three walls. Still got 30 square feet done. Now the good news: there are only 4 more
courses to go, which I calculate to be about 48 square feet. Unfortunately, I estimate that there are only
about 50 square feet of shingles still in boxes. It’s gonna be close…
12 July 2019
Late in the afternoon a chipmunk ran into the
barn through the open people door in the north wall. The critter stopped to give me the “I’m so
cute, don’t hurt me” eyeball, before proceeding under the trailer, hopefully not
intending to take up a new home there. I
quickly opened the overhead garage door, thinking Mr. Munk might take the 16
foot wide hint. Time will tell! Put another 30 square feet of shingles on the
west wall before breaking off to get the house ready for dinner guests (Marty
and his daughter, Heather Glassner).
11 July 2019
Even though she ain’t pretty, by using nearly
every scrap piece of Slicker Classic® left from the other three
walls, was able to cobble together coverage for the remainder of the west
wall. When the cobbling was done, had just
5¼ square feet of yellow mesh left. Now
that’s good planning! (…or just lucky,
take your pick.) By being cheap
frugal, didn’t have to open the next full roll… each of which retails for $117.70. So two rolls can be returned to Goodro’s for
credit, which means I’ll need to find another project to use that credit
towards. Oh, darn! During the expected early afternoon
thunderstorm, stayed dry in the shop turning a bunch of 8″+ shingles into
desperately needed 3″ and 5″ sizes. Come
quitting time, another 26 square feet of the west wall had been shingled.
10 July 2019
After a lengthy hiatus visiting family and
enjoying a cruise from Rhode Island to Maine with Doug & Kathy O’Brien
aboard EAGLE FORD, got back to work on the barn today. Another 15 square feet of shingles stapled onto
the west wall, including the small triangle on the northwest corner. Have been fretting about how to do that triangular
piece for months now. When the time came
to actually do the deed, just faked it one shingle at a time, with some help
from Chree. Came out okay… but I’m sure
there must be some old Indian trick known by professionals. Our dock has emerged, once again, from
beneath the lake; two weeks ago, after some hefty rainstorms, the top of the dock
was 2½″ under water. The water
temperature now is a delightful 79°F.
Subscribe to:
Posts (Atom)