30 June 2014

At 6:20 (luckily I was up and dressed), Dave Todd (across the street neighbor) knocked on the RV door and presented me with a quart of ripe strawberries as a thank you for the use of my trailer last week. Perry arrived at 6:40 to get set up for replacing me on the construction team for the next few weeks. Sean and Ian got here at 7, per usual, and the three building experts began assembling and putting up the Garage south and east walls. I left at 7:10 with the Ranger, Mr. Jonsered, and mouse #6 on a winding journey, first to Green Mountain Garage in Brandon to have the Ranger fail inspection (bad bearings in the front left wheel), then to Champlain Valley Equipment in Middlebury to drop off the chainsaw for repair, then to Silver Lake to release the mouse.  Got back to Fern Lake at 9 and got down to some serious cleaning of Dolores’ innards, with occasional breaks to fetch and carry for the construction crew.  Sean left at noon, so after lunch I joined the fun in the sun until Chree arrived at 2, bringing with her Geisha (our 12 year old German Sheppard) and Shlomo (our acts-like-a- puppy 5 year old Black Lab).  Soon thereafter Shlomo snuck off down the hill and cooled off in the lake, but then came right back… to roll in the dirt and sawdust of the building site. Chree and I toured the house, making decisions about window and door details (Sean is still batting 1.000 with his recommendations!), then she and the dogs retired to the comfort of air conditioning in the RV.  Just at quitting time the Goodro’s truck arrived with another mega-thousand dollar load of lumber… with more promised for tomorrow!  Once everyone was gone, the dogs and I partook of a refreshing swim while Chree enjoyed the waterfront ambiance… with occasional showers from a certain black doggie who has learned to cannonball.  Lake temperature is up to 79°.

29 June 2014

Not only did Dolores start right up (using the coach batteries, the truck battery being completely flat after nine months of sitting), but the slide-out came all the way in.  (That’s only because I’ve made an appointment to have the slide-out repaired next week at Pete’s RV in Burlington).  She and I trundled up to Kampersville for a good purging, then I gave her a bath back at Fern Lake because she needed it desperately had been such a good girl.  Spent the remainder of the day over at Lynne & Perry’s doing five loads of laundry, cutting and splitting wood (so much more challenging in the blazing hot sun), and finding out that Mr. Jonsered has a serious gas leak somewhere in his innards, hence the starting and performance problems seen after he has fully warmed up.

28 June 2014

Cinquo de mousy took a one-way trip to Silver Lake right after breakfast.  Then there was a tremendous beaver attack between the house and lake.  Unfortunately, and very frustratingly, the beaver got a toothache after the third tank of gas… wouldn’t start, then, if it did start, wouldn’t rev up, then, if it finally would rev up, worked fine until I shut it off, then wouldn’t start…  Got all but one tree down, which helped the view from the house somewhat, though considerable limb removal will next be in order.

 

27 June 2014

Sean & Ian, with cutting and carrying help from me, built and put up all of the remaining walls for the Main Level house shell except for the east and south walls in the Sun Room and the Garage.  The Sun Room east wall is awaiting a decision about door and window placement, to be made soon after Chree arrives on Monday.  The Sun Room south wall, being a full gable, can’t be built until the roof rafters are in place, as the studs for that wall have to be custom cut to fit under the rafters.  The Garage walls are Monday’s project.

 


26 June 2014

Stopped raining at 5 am, but then misted heavily until early afternoon.  Relocated mouse 14-4 to Silver Lake right after breakfast.  Sean, Ian and I spent the day building and erecting the framework for the Main Level west wall and that portion of the north wall that will enclose the Master Bedroom.  The three of us put up the Living / Dining wall as one piece… very heavy with the huge header over the 12+ feet of windows in that room and, of course, the wall had to be positioned right on the edge of a 9 foot drop.  Tricky, but then, again, Sean and Ian seem to know all the tricks.



25 June 2014

As predicted, a totally rainy day, so the Goose stayed away, hopefully in dryer climes.  Went into Middlebury first thing to move Mr. Jonsered from gathering dust at Taylor Rental to, hopefully, having his ailment attended to more promptly at Champlain Valley Equipment.  When I got to Taylor Rental, Chris, the manager, said that my chainsaw would be fixed “today”.  With that assurance, left the saw in his capable hands and returned to Fern Lake.  Two hours later, Chris called to say my saw was ready for pickup.  Guess sometimes the squeaky mouse does get the cheese.  Problem was $50 worth of “crap” in the carburetor, as originally suspected.  Spent the remainder of the day tweaking the house design to accommodate some size differences between the foundation that actually got built and what the architect envisioned.  When working to 1/16″ tolerances, a garage that is 6″ shorter and 6″ wider than designed causes some major perturbations in the Force.  Fortunately, Sean (as usual) not only had some great ideas about how to fix the resultant design problems, but also suggested some tweaks to window and door placement and sizes to make the exterior appearance of the house much more pleasing to the eye.  Opened a new bottle of JWB mid-afternoon…

24 June 2014

Sean got here at 7 and put together a cut list for the Main Level door and window headers, which I got busy producing.  At 8:15 it started raining (earlier than expected, but as forecast), so we secured everything for heavy weather and Sean prepared to depart.  At that point it stopped raining, though Sean’s smart phone weather radar app showed plenty of moisture supposedly headed our way within a couple of hours.  We started work again, Sean laying out the stud, jack, and cripple placement for the walls and me making long lumber into shorter lumber.  A few sprinkles, but nothing serious until just before lunch.  With everything once again covered up, Sean and I enjoyed a gourmet luncheon (left over from last night’s repast) in Dolores’ dry confines, figuring we were (once again) done work for the day.  The sun came out (briefly!), so back to work we went… though we weren’t amovin’ any too fast after that heavy meal.  Only occasional light sprinkles all afternoon.  Just before quitting time the Goodro’s truck arrived with a delivery ordered for tomorrow morning.  Sean must be slipping, ‘cause there was less than $1,000 on the invoices I signed after we offloaded the “stuff”.

23 June 2014

Sean and Ian pulled in at their usual ungodly (for us retired folk) hour.    While waiting for the Goodro’s truck to arrive with another umpteen-thousand dollar load of materials needed for the next construction phase, Sean did some heavy thinking about the layout of the Main Level exterior walls while Ian and I put the two steel / concrete posts in place under the long steel beam.  Then Ian got busy sawing notches in the between-joist braces to clear the way for me to drill four ¼″ holes through the lower flange of each beam so that the top plate of each post could be bolted to the flange.  Arduous work, which took all morning, even with brand new, top quality drill bits.  Sean says the main level floor looks flat (but did he have his eyes shut when he “looked”?), so maybe I did cut the posts to the correct lengths…  Sean and Ian, meanwhile, started tacking in place the sole plates for the exterior main level walls, checking to ensure that they formed perfectly square (so, okay, the long diagonals were 1/16″ different!) rectangles of the correct sizes.  Late afternoon, as we were finishing that work, Kevin Betourney and Brian Dunleavy, from Kevin's Roofing, came by to scope out the standing seam metal roofing jobs (house and sauna) that will need to be done later this summer.  Sean asked Kevin to give us two estimates: one to do the roofs like the woodshed was done and one to do the roofs like Kevin would normally do them.  Kevin mentioned in passing that we would need a cricket on the upslope side of the house chimney.  The architect (who at this point should be taken out and shot) said, no, the chimney was rotated 45°, causing all sorts of hate and discontent with the house design, specifically so that no cricket would be needed.  Whereupon Sean and Kevin showed why, if the chimney were in a “normal” position, water would flow away from it on all sides (so no cricket needed), but because it has been twisted, water could get trapped on the upslope side, which would necessitate putting in a cricket.  Chrip, chirp…  Early quitting time today so I could prepare another fabulous lasagna dinner for Marty & Merry… and start drinking.


 

22 June 2014

Vacuumed, washed, waxed, then parked the Ranger along Lake Dunmore Road up at the head of the driveway with a big For Sale sign taped to the driver’s window.  The phone should start ringing with offers any minute now…  Applied Geocel under the steel beams and to the seam between the west wall sill plate and the cellar floor.  Ran out of the tube I was using, of course, with 1 foot left to go!  Discovered that there was a 1/16″ difference over 10″ between my “good” carpenter’s square and Ian’s big framing square.  As it was obvious last week that the radial arm saw, so carefully aligned using my “good” square, was not cutting straight, completely realigned the saw using Ian’s square.

21 June 2014

Into Burlington to pick up a special order of Cabot Weatherizing Stain 3244 (for the Sauna siding), spend money at Lowe’s, and visit with Alverta, who treated me to lunch.  Upon return to Fern Lake late afternoon, found that I had captured yet another mouse, who now resides with his/her friends at the Silver Lake parking area.  Patched the concrete floor areas that were chipped when the west wall sill plates were installed, ‘cause the floor was poured higher than the frost wall and the sill plates overlap both… and had to be made to sit level.

20 June 2014

A very productive day… with perfect weather!  Ian and Ben got here at 7 and resumed putting in mid-span joist braces.  I finished cutting the special sloped joists that will be under the main entry porch. Sean appeared bringing gifts from Goodro’s: lots of hangers for me to install where joists were attached to other joists. Sean, Ben, and Ian installed the ¾″ (technically it’s only 23/32, if you want to quibble) AdvanTech® tongue & groove subflooring for the main level of the house.  Ty came to join the fun mid-morning.  Because the architect (that would be me) specified that the subfloor be both glued and screwed (vice nailed) to the joists, you’ll never guess who got assigned to put in the 2,000+ screws needed to hold down 1,640 ft2 of AdvanTech®?  Went through four charges on the battery for my impact driver (and my back may never be the same) before that job was done… and I had help from Ty and Ian at various points during the almost-all-day, quite brutal process.  I can hear the bed calling already…





 

19 June 2014

Ian pulled in at 7, per usual, then got busy putting in the mid-span joist braces.  I fetched for him between trimming off all the shims that were used to level the west wall rim joist and then putting new shims between each joist and the west wall top header plate (so that the joists are resting solidly on wood vice just hanging on the nails that hold them to the rim joist).  Sean had some early morning meetings and had to stop at Goodro’s to increase the balance on my account, so didn’t arrive until 10.  He and Ian spent the remainder of the day installing virtually all of the rest of the ceiling / floor joists, with me cutting and trimming as they needed that done.  Beer and steak consumed, relocated yet another mouse to the Silver Lake parking area.

18 June 2014

A wicked good thunderstorm overnight left a nice swimming pool in the cellar.  Some earnest activity with the push broom soon lowered the water to wading level...  and then Ian cut and removed the sill and sole plates for the Shop door, so further flooding should only be moderately deep.  Sean and Ian spent the day installing Lower Level ceiling / Main Level floor joists.  The Goodro’s truck arrived just after 8 with the next installment from our kid’s inheritance.  From the lumber thus delivered, I spent the morning mass producing 200 2x8x147/16 blocks that are used to brace the joists mid-span and where they rest on the steel beam flanges.  Sean, in his proper role as adult supervisor, astutely caught a 1″ error in the measurements for the chimney placement that directly affected the joist layout.  Glad somebody on this job knows what he’s doing!!!!  Jim LaFlam stopped by mid-morning to check on progress.  Sweating bullets, inhaling Tums, and with all ten fingers crossed, I cut to length the two posts that will support the long steel beam.  The posts are made from steel filled with concrete… and you only get one chance to get them the correct length… which has to be exactly right or the Main Level floor will not be level.  No pressure!




17 June 2014

Turns out that Sean caught what would have been the 6th largest salmon in the tournament, but they ate the fish instead of taking it in for official measuring.  Sean and Ian (with some help from me sawing and lugging), built and erected the Lower Level west wall framework.  Even though this is “rough” carpentry, they are working to 1/16″ (or less) tolerances on every joint… most impressive.  At the end of a very hot afternoon, we used the Tacoma’s automobile jack to remove the sag in the long steel beam, then set a temporary wood post to hold the beam in position until the permanent posts are installed (tomorrow).  Lake temperature is up to 77°; almost perfect!

16 June 2014

Scheduled holiday for Goose Creek Builders – final day of the Lake Champlain Fishing Tournament.  Applied Geocel® Pro Flex clear caulking sealant (guaranteed to last 50 years) to the interior side of the sill plate / concrete wall seams.  Cut 32 2x10x142⅜ floor joists.  The pile of uncut 2x10’s has been overrun with carpenter ants and a zillion eggs.  Captured, then relocated to the Silver Lake parking lot, one very fat mouse.

13 - 15 June 2014

Went down to CT for the funeral of Chree’s 99 year old aunt and godmother, Norma Bradford.  She will be missed!  Was nice to see Chree again, however briefly, two weeks earlier than expected.  Got back to Fern Lake early afternoon on Father’s Day and performed a complete alignment procedure on the radial arm saw.  The Lapidii had me down to their place for a roast chicken dinner that was great (company and food), as always.

12 June 2014

Sean and Ian arrived shortly after 7, eyeballed the wet and dreary weather conditions, chatted for awhile, and were gone by 8.  I went ice cream shopping in Brandon, then headed to Burlington to spend money at Lowes, tackle some repairs at the condo we own there, and attend Alverta’s 90th birthday celebration, held at Pauline’s Restaurant (her favorite).  Back to Fern Lake just in time for bed, discovering upon arrival that the Long Ridge crew had removed the revival tent from over the newly poured Garage floor.

11 June 2014

Ian arrived at 7, as expected, but then so did Rick and Kevin… obviously Larry had decided to pour the Garage floor today.  The rest of the Long Ridge crew (Larry, Victor, Scott, & Ben) pulled in shortly thereafter.  Ian and I continued cutting and notching floor joists, with Ian also cutting studs for the west wall during breaks in the action. Sean arrived and resumed laying out the west wall top and bottom plates.  Jimmy came with a bill and I paid him for his excavation work over the past few weeks. Sometime before 9 a Carrara mixer showed up with just over 7 cubic yards of 4,000 psi concrete.  Late morning, again just as the concrete had set enough for finishing, the rain started.  Bet you saw that coming! Rick and Kevin quickly threw some tarps over the floor, hoping that it was going to be only a brief shower.  (Can you hear the hollow laughter in the background?)  Sean, Ian, and I secured the carpentry worksite and took an early lunch in the RV.  By noon the weather radar was looking downright ugly, so Sean and Ian called it quits for the day.  Sean went away smiling with the first installment of the contract management fee tucked into his wallet.  Larry came back shortly thereafter and the four of us erected a nice revival tent over the Garage floor so that Rick and Kevin could finish floating the floor in spite of the inclement weather… which they had done by 3:30.  Figured the rain would stop then, but it didn’t…









10 June 2014

Sean & Ian were here by 7:30; the Goodro’s big boom truck, fully loaded with many $ thousands of lumber, flooring, and 3 steel beams, got here just after 8.  First order of business was to swing the 3 beams into their approximate positions on the cellar walls, which the boom truck accomplished easily.  With all the other Goodro’s goodies offloaded, Sean and Ian notched the sill plates to accept the beams.  Then I, clever boy that I am, managed to single-handedly knock the long beam onto its side… and nearly down onto the cellar floor.  Major disaster narrowly averted by pure happenstance.  Used the Kubota in forklift mode to right the beam, but then, to get it into its notches, had to lift the beam using the top of the grid that holds the forks to get enough weight off the beam for Sean and Ian to move it, very carefully, into position.  Balancing a 700 pound, 44 foot long, 4″ wide beam on a piece of steel 2″ wide by 36″ long is one of those things they tell you on TV not to try at home.  Many gray hairs later, with all beams in their final resting spots, we measured less than ⅛″ difference in their top elevations.  A few hours after that all the rim joists were in place.  After lunch I moved my radial arm saw into the area that will become the Shop. Boy is it nice to finally have a level place, with plenty of room, to operate the saw! Ian and I went into production mode creating floor joists.  Each one, obviously, has to be cut to a precise length to fit between the steel beams (my job), then the top corners had to be notched to exactly fit around the top flange of the beams (Ian’s job).  Meanwhile, Sean started to lay out the top and bottom plates for the west wall, discovering that the two concrete end walls are exactly 60 feet apart top and bottom (as they should be), but both are leaning to the north by ½ inch.  Oops!  So, instead of building a wall to fill a rectangular space, Sean will be constructing a parallelogram.  He needed a little challenge in his life.  A threatening thunderstorm (that blew over without precipitating), raging thirst, and low carbohydrate levels put an end to the day’s endeavors.






9 June 2014

Sean and Ian"Yukon" Birkett arrived just before 9 bearing a truckload of 2x6x12 PT which became, over the course of the day, sill plates for the house.  The sill plates were fastened to the foundation walls using the embedded ½″ galvanized J-bolts and a thick bead of Lumber Lock construction adhesive. Used the Kubota as a improvised clamp to hold down two of the 2x6’s that wanted to bow up when first installed on one of the Garage walls. We discovered that the foundation walls were exactly the length they were supposed to be and were only out of square ⅛″… which is pretty darn impressive!  Thank you, Larry Kaufmann and the Long Ridge crew, for a concrete job exceptionally well done!!!!  Between beers with the boys and a much-needed cool-down swim, helped Dave Todd move a bunch of firewood from a seasoning stack into Kate’s woodshed.

8 June 2014

John and Mary Jane Cuneo, friends from when we lived in Bradford, MA, came for lunch-on-the-grill and a swim.  Hadn’t seen them in person for 24 years, though annual holiday newsletters had kept us in touch with each other’s lives over the intervening two decades.  Can’t say they had changed much…  A delightful visit, hopefully repeated again soon, as they have strong ties to the Middlebury area.  In the evening, shared a pre-prandial bottle of wine with Kate and her weekend guests.

7 June 2014

Larry arrived sometime before I finished breakfast to cut control joints in the cellar floor slab.  When (not if) the cellar floor cracks, in theory it will do so along the saw cuts (deliberately weakened areas) Larry made… which just happen to be under where walls will be placed. That’s why they’re called control joints. Clever, huh?!?!  Spent most of the day at Lynne & Perry’s doing laundry.  But call me Mr. Jinx.  After refueling from burning the first tank of gas cutting up logs for their firewood, Mr. Jonsered would start, but as soon as the throttle trigger was pulled, died.  Figuring maybe the older gas that I had refueled with had gone bad (even though it had been treated with a double dose of Stabilfuel), put in fresh gas.  Saw started, made a bunch of cuts, turned it off, and it then refused to start.  This was at 11:30, with Taylor Rental (Jonsered authorized service / repair center) closing at noon on Saturdays.  So beat feet rapidly in their direction.  Preliminary diagnosis is “crap” (a techno-speak repair term) in the carburetor jets.  Returned to Lynne & Perry’s, where we broke out Perry’s Jonsered.  While I was continuing to cut logs, that machine started smoking like it was on a two packs a day habit.  Determined that there is a gasoline leak somewhere in its guts.  Not so good!  Taylor Rental will be getting another Jonsered corpse come Monday.  We then fired up Perry’s log splitter which… worked just fine.  Whew!  One pickup truck filled to the brim with split hardwood later, headed for the cool enjoyment of Fern Lake... and clean sheets on the bed tonight.  Parked the Tacoma in the garage for the first time, just because I could.  Before doing so, was thinking the garage might be a trifle oversized.  It’s not!


6 June 2014

So Larry didn’t want to pour the cellar floor slab on Wednesday because the weather was supposed to be unsettled after a frontal passage Tuesday night.  The weather Wednesday was fabulous.  Then Larry didn’t want to pour yesterday because there was a 40% chance of showers, but only a 20% chance today.  Yesterday also was gorgeous.  Today I awoke to the pitter patter of raindrops falling on Dolores’ head.  The drizzle persisted most of the morning.  The concrete trucks started rolling in at 8 and by 10 there were 20 yards spread around in the cellar (plus a half yard in the sauna).  At noon, just when Larry and crew wanted to start the final smoothing of the floor, the rain came down hard for 15 minutes or so, turning the cellar into a soggy mess.  Fortunately, no further rain fell the remainder of the day and, after sweeping the excess water off the floor with a push broom, the Long Ridge crew were able to resurrect the floor.  Meanwhile, Jimmy was here all day backfilling around the Garage frost walls, prepping the Garage floor for a concrete pour sometime next week, and doing some grading around the house foundation so that Sean can put up scaffolding sometime in the not so distant future.  Had a nice chat with Kate, who is up for the weekend.  Marty & Merry invited Kate and me down for another great dinner á la Restaurant Formidable Lapidus.


 




5 June 2014

A thoroughly miserable day.  Not the weather, the job.  As the cellar floor concrete pour was postponed another day (‘cause the weather, which was beautiful, was forecast to be not), decided to tackle replacing the errant tee in the perimeter drain with a proper wye.  Why not?  Seemed simple enough, just use the backhoe to dig down to the fitting and couplings, undo the latter, wave my magic wand, and presto change-o.   Only problem was that the backhoe only digs six feet something and the fittings were eight feet something under compacted stone.  So the last two feet were pure misery… aided and abetted by the banks collapsing several times… always at critical junctures.  Got the job done, but will definitely sleep well tonight.  Jimmy showed up (twice) late afternoon to drop off equipment for tomorrow’s festivities.  Just how many excavators does that guy own????


4 June 2014

Woke up at 5 with the horrible realization that the house design had the steel beams in the wrong places from the perspective of both load balance and efficient use of materials.  Quickly designed a solution, but that fix potentially impacted many other facets of the house construction… including Sean’s floor joist layout.  Fired off an email to Sean at 6, asking him to boogey on over to Fern Lake ASAP.  Kevin and Victor got here just before 8 and, by 10, had dismantled the Garage frost wall concrete forms and were back over the horizon.  Sean got here at 8, then we spent a couple and a half hours looking at all the impacts of moving the beams. Bottom line is that the toilet and window in the Master Bath had to move westward, the staircase will have to slide east a few inches, and the footers for the posts supporting the long beam will have to be re-poured (which can be done the same time the cellar floor slab is poured). But, now the load on each beam is well balanced and there will be minimal wastage when we install the Main Level floor joists.  After Sean left, I got to work digging (literally by hand) the new holes for the post footers and lining them with 6 mil polyethylene sheeting.  That was done by noon.  Fortunately, the already-installed radiant floor tubing was easily rerouted around the new holes.  Called to complain about the burgeoning mosquito population and the failure of the BLSC driver to spray down this way when last he/she was in the neighborhood.  Spent most of the afternoon running errands in Middlebury and Brandon, then doing more cleaning and organizing in the woodshed / temporary workshop / underground bunker.

3 June 2014

Back to Goodro’s first thing to put the final color coat on the two 19′ 9″ steel beams.  Also picked up a 4″ x 4″ SDR light-wall wye-coupling (not to be confused with a regular SDR wye-coupling – which costs 6-times more) to replace the tee-coupling we put in, by mistake, for the roof valley drain.  Got back to Fern Lake just before 9 to find that Fyles Brothers had already come and gone, leaving 14.1 gallons of propane in Dolores’ gizzards. Kevin and Scott came just before 11 to pull apart the garage frost wall footer forms.  Larry and Victor got here an hour later and the Long Ridge crew put up the frost wall forms and rebar, pinning the latter into the cellar foundation walls.  Chuck pulled in at 2 to put 40 psi of air pressure on all the radiant floor PEX tubing… testing for any installation leaks (none) and to identify any leaks created during the concrete floor pour later this week.  I filled in a few shovelfuls of dirt around the sauna drain, set the drain so it is perfectly level, then put some scrap Blueboard around the edges to serve as expansion joints for the sauna floor (which, obviously, will be subjected to some major temperature swings and commensurate expansion and contraction).  A Carrara mixer delivered 5 cubic yards of 3,000 psi concrete at 2 o’clock.  By 4, with the Garage frost walls filled and floated, the Long Ridge gang was packed up and gone, so I took a quick plunge ahead of the line of thunderstorms bearing down on Fern Lake from the west.  Made it back to the shelter of the RV with minutes to spare.

2 June 2014

Rolled out of bed at 6:45 which meant, of course, that Sean pulled in right when he said he would… while I was still slurping coffee and calories.  We discovered that some interesting spray foam sculptures had arisen from Blueboard gaps where I had, obviously, been a little heavy handed on the trigger.  Sean and I laid out the three heating zones on the house lower level (and the no heat area under the Wine Cellar Nook and Cedar Closet), marking the wall positions on the blue foam insulation with orange spray paint.  Very colorful!  Kevin and Ben from Long Ridge got here at 8 and started putting together the forms and rebar for the Garage frost wall footers.  Chuck arrived at 9 and he, Sean, and I quickly designed the layout for the in-slab radiant floor heat, which uses ½″ PEX tubing.  [Warning, construction details! Ideally, each tubing run should be 9″ from adjacent runs or a wall and each loop of tubing should be no more than 250′ long.  Doing the math with a 1,640 square foot cellar, that would mean using about 2,050 feet of tubing in 8 loops.] I worked with Chuck on the actual installation, finding ways to get the job done with about 1,400 feet of tubing in 6 loops.  A short time after Sean left, Larry, Victor, and Scott came rolling in.  Larry  gave me the invoices for work performed to date and I wrote the first (of many!!!!) mega-thousand dollar checks in payment.  Urp! On a positive note, Larry gave me credit (at his regular labor rate) for the hours I contributed during the cellar concrete wall construction.  A Carrara mixer came at some point and, next thing I knew, the Long Ridge crew was gone and there was fresh concrete in the forms.  Guess Chuck and I were just having too much fun in the sweltering sun.  By 2 o’clock all the PEX tubing was in place, so Chuck left, leaving me to fabricate PVC sleeves for where the tubing will enter and exit the cellar floor slab and a rebar support bar and posts to hold those sleeves in place during the cellar floor concrete pour.  Hit the lake (which is up to 70°) as soon as that was done and the area cleaned up.

 


1 June 2014

Arose at 6:30 and departed a still slumbering Chez Lapidus to find two and a half very much awake and hungry people in the RV.  After fortifying ourselves with omelets, Alex cut, then he and I split, then Katy and I stacked a quarter cord of campfire wood.  Devin sampled the flavors of rocks down by the cellar but, unfortunately, found one that didn’t agree with him, causing Katy to have to change both his and her clothes.  While the three younger Perkins tested the waters down at the dock, I did some baking so we would have enough calories for lunch.  Just as we were finishing our mid-day repast, Perry arrived to bid the Boston folks au revoir… and take a look at construction progress made over the past several weeks.  Everyone headed towards home at 1:30, whereupon I swept the cellar insullation semi-clean of debris, then applied four cans of low-expansion foam to all the Blueboard gaps and cutouts.  Hopefully the trigger finger on my right hand will regain feeling sometime later this month…